ROAD AND LANE CLOSURES FOR FEB 2 - FEB 9


Here are the major scheduled road and lane closures for Monterey County from Sunday, February 2, through Sunday, February 9, 2014 – newest information is in red. Please keep in mind that construction work is weather-dependent.

Highway 1 – Multiple Locations:  Feb. 3 – Feb 7
  • Daytime drainage and tree work at multiple locations along Highway 1 between from 8:30 a.m. to 3 p.m.
  • Locations are:
    • Lime Creek Bridge to Big Sur Maintenance Station: drainage work.
    • Burns Creek Bridge to Castro Canyon Bridge: tree work.
    • Big Sur Maintenance Station to Garrapata Ridge Road: drainage work.
  • Motorists can expect delays of approximately 10 minutes.
Highway 101 – Gonzales and Soledad:  Feb. 3 – Feb. 7
  • Daytime drainage and median work on Highway 101 from La Gloria Road to Arroyo Seco Road will result in alternating lane closures—northbound and southbound—between 4 a.m. and 4 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Prunedale Improvement Project: Feb. 3 – Feb. 7
  • Nighttime work will result in alternating lane closures on northbound and southbound Highway 101 between Vierra Canyon Road and Crazy Horse Canyon Road from 7:30 p.m. and 6 a.m.
  • Motorists can expect delays of approximately 10 minutes.
San Juan Road Interchange: Feb. 3 – Feb. 7
  • Night work on Highway 101 will cause alternating lane closures on northbound and southbound Highway 101 between Dunbarton Road and Rocks / Cannon Road from 7:30 p.m. and 6 a.m.
  • Motorists can expect delays of approximately 5 minutes.
Special Notice — South County: Jan. 23 – Feb. 6
·        Military training exercises will cause delays on Milpitas Road and Nacimiento Fergusson Road in Fort Hunter Liggett Jan. 23 – Feb. 6.
·        Rail road repairs will cause delays on Sargents Road in San Ardo Jan. 23 – Feb. 6.

Friday, January 24, 2014

ROAD AND LANE CLOSURES FOR JAN 25 - FEB 2

Here are the major scheduled road and lane closures for Monterey County from Saturday, January 25, through Sunday, February 2, 2014 – newest information is in red. Please keep in mind that construction work is weather-dependent.

Highway 1 – Bixby Bridge:  Jan. 25
  • Daytime guardrail repair near Bixby Bridge between from 9 a.m. to 3 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 1 – Multiple Locations:  Jan. 27 – 31
  • Daytime drainage, tree removal, vegetation spraying, and shoulder work at multiple locations along Highway 1 between from 8 a.m. to 3 p.m.
  • Locations are:
    • Hot Springs Creek Bridge to Castro Canyon Bridge: drainage clearing.
    • Lime Partington Ridge Road to Castro Canyon Bridge: tree removal.
    • Big Sur State Park Entrance to Garrapata Ridge Road: drainage clearing.
    • Malpaso Creek Bridge to Highway 156: vegetation spraying.
    • Highland Drive to Granite Canyon Bridge: shoulder work.
  • Motorists can expect delays of approximately 10 minutes.
Highway 1 – Monterey:  Jan. 30
  • Daytime maintenance work on the northbound Highway 1 off ramp at Fremont Street from 9 a.m. to 3 p.m.
  • Motorists can expect delays of approximately 5 minutes.
Highway 68 – Pacific Grove:  Jan. 21
  • Daytime paving on Highway 68 between 17 Mile Drive and Grove Ave. from 9 a.m. to 2 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 101 – Gonzales and Soledad:  Jan. 27 – Jan. 31
  • Daytime drainage and guardrail work on Highway 101 from La Gloria Road to Arroyo Seco Road will result in alternating lane closures—northbound and southbound—between 4 a.m. and 4 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 101 – Salinas:  Jan. 28 – Jan. 31
  • Daytime guardrail work on Highway 101 from Alisal Road to Sherwood Drive between 9 a.m. and 3 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Prunedale Improvement Project: Jan. 27 – Jan. 31
  • Nighttime work will result in alternating lane closures on northbound and southbound Highway 101 between Vierra Canyon Road and Tustin Road from 7:30 p.m. and 6 a.m.
  • Motorists can expect delays of approximately 10 minutes.
San Juan Road Interchange: Jan. 27 – Jan. 31
  • Night work on Highway 101 will cause alternating lane closures on northbound and southbound Highway 101 between Dunbarton Road and Cole Road from 7:30 p.m. and 6 a.m.
  • The night work will also cause temporary closures of the San Juan Road off ramp 7:30 p.m. and 6 a.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 218 – Seaside and Del Rey Oaks:  Jan. 31
  • Daytime vegetation spraying on 218 between Del Monte Blvd and Highway 68 from 9 a.m. to 2 p.m.
  • Motorists can expect delays of approximately 5 minutes.
Special Notice — South County: Jan. 23 – Feb. 6
·        Military training exercises will cause delays on Milpitas Road and Nacimiento Fergusson Road in Fort Hunter Liggett Jan. 23 – Feb. 6.
·        Rail road repairs will cause delays on Sargents Road in San Ardo Jan. 23 – Feb. 6.

Friday, January 17, 2014

ROAD AND LANE CLOSURES FOR JAN 18 - JAN 26


Here are the major scheduled road and lane closures for Monterey County from Saturday, January 18, through Sunday, January 26, 2014 – newest information is in red. Please keep in mind that construction work is weather-dependent.

Highway 1 – Multiple Locations:  Jan. 20 – 24
  • Daytime drainage, slide removal, paving, and tree work at multiple locations along Highway 1 between from 8 a.m. to 3 p.m.
  • Locations are:
    • Wild Cattle Creek Bridge to Rain Rock: slide removal.
    • Lime Creek Bridge to Partington Ridge Road: drainage clearing.
    • Big Sur State Park Entrance to Point Sur Naval Facility: drainage clearing.
    • Rocky Creek Bridge to Garrapata Ridge Road: crack and seal work.
    • Highland Drive to Granite Canyon Bridge: tree and shoulder work.
  • Motorists can expect delays of approximately 10 minutes.
Highway 1 – Moss Landing:  Jan. 18
  • Daytime pavement work on northbound Highway 1 at Elkhorn Slough Bridge from 6 a.m. to 12 p.m.
  • Motorists can expect delays of approximately 15 minutes.
Highway 1 – Moss Landing:  Jan. 21
  • Daytime maintenance work on Highway 1 at Hilltop Industries from 9 a.m. to 2 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 101 – Gonzales and Soledad:  Jan. 20 – Jan. 24
  • Daytime drainage and guardrail work on Highway 101 from La Gloria Road to Arroyo Seco Road will result in alternating lane closures—northbound and southbound—between 4 a.m. and 4 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Prunedale Improvement Project: Jan. 20 – Jan. 24
  • Nighttime work will result in alternating lane closures on northbound and southbound Highway 101 between Vierra Canyon Road and Tustin Road from 7:30 p.m. and 6 a.m.
  • Motorists can expect delays of approximately 10 minutes.
San Juan Road Interchange — Crossover, Road and Lane Closures: Jan. 20 – Jan. 24
  • Temporary night time traffic crossover on Highway. 101, between Dunbarton Road and Cole Road, Monday, January 20 and Tuesday, January 21.
  • Night work will also temporarily close access to and from San Juan Road at Highway 101 starting Monday, January 20 and going through the mornig of Thursday, January 23.
  • There will also be alternating lane closures on northbound and southbound Highway 101 between Dunbarton Road and Cole Road on Wednesday, Thursday, and Friday.
  • The crossover, road and lane closures will occur between 7:30 p.m. and 6 a.m.
  • Motorists can expect delays of approximately 15 minutes.

NIGHT WORK ON US 101 AT SAN JUAN ROAD WILL AFFECT TRAFFIC January 20 – 21


Work on the new San Juan Road Interchange will shift traffic on Highway 101, between Dunbarton Road and Cole Road to the other side of the highway beginning January 20. The work will also temporarily close access to and from San Juan Road at Highway 101.

The lane switch and road closure will occur between 7:30 p.m. and 6 a.m. Monday, January 20 and Tuesday, January 21.

Motorists should detour to San Miguel Canyon Road.

Traffic on both northbound and southbound Highway 101, and San Juan Road will be affected; detour signs will indicate the closure and the shift of the traffic to the opposite side of the highway through the construction area.

The traffic crossover and temporary road closure is necessary to allow crews to install temporary concrete barriers for work on the center divider.

The San Juan Road Interchange Project will improve safety and reduce congestion on U.S. Highway 101 between Dunbarton Road in Monterey County and Cole Road in San Benito County. The $69 million project will remove three major at-grade intersections (San Juan Road, Dunbarton Road, and Cole Road) and replace them with a new interchange near the Red Barn at San Juan Road and U.S.101. The project is supported by $10 million from the Recovery Act and $28 million from Proposition 1B, a 2006 voter-approved bond. In total, nearly $15 billion in Proposition 1B funds have been distributed statewide.

Friday, January 10, 2014

ROAD AND LANE CLOSURES FOR JAN 12 - JAN 19


Here are the major scheduled road and lane closures for Monterey County from Sunday, January 12, through Sunday, January 19, 2014 – newest information is in red. Please keep in mind that construction work is weather-dependent.

Highway 1 – Big Sur Coast:  Jan. 13 – 17
  • Daytime drainage, slide removal, and utility work at multiple locations along Highway 1 between Pacific Valley and Big Sur from 8 a.m. to 3 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 1 – Granite Canyon Bridge:  Jan. 17
  • Daytime pavement work on Highway 1 at Granite Canyon Bridge from 9 a.m. to 2 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 1 – Yankee Point:  Jan. 16
  • Daytime tree removal on Highway 1 between Malpaso Creek Bridge and Yankee Point Drive (North) from 9 a.m. to 2 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 1 – Point Lobos:  Jan. 13 – 14
  • Daytime tree removal on Highway 1 between Jose Creek Bridge and Point Lobos State Reserve from 9 a.m. to 2 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 1 – Monterey:  Jan. 15
  • Daytime pavement marker replacement on Highway 1 between Casa Verde Way and Del Monte Avenue from 9 a.m. to 12 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 101 – Gonzales and Soledad:  Jan. 13 – Jan. 17
  • Daytime drainage and electrical work on Highway 101 from La Gloria Road to Arroyo Seco Road will result in alternating lane and ramp closures—northbound and southbound—between 4 a.m. and 4 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 101 – Salinas to San Benito County:  Jan. 13 – Jan. 17
  • Daytime road sweeping along highway 101 from Airport Boulevard to the San Benito County Line between 9 a.m. and 3 p.m.
  • Motorists can expect delays of approximately 8 minutes.
Prunedale Improvement Project: Jan. 13 – Jan. 17
  • Nighttime work will result in alternating lane closures on northbound and southbound Highway 101 between Vierra Canyon Road and Tustin Road from 7:30 p.m. and 6 a.m.
  • Motorists can expect delays of approximately 10 minutes.
San Juan Road Interchange – Cannon Road to Dunbarton: Jan. 13 – Jan. 17
  • Nighttime removal of bridge falsework will result in alternating lane closures on northbound and southbound Highway 101 between Cannon / Rocks Road and Dunbarton Road from 7:30 p.m. and 6 a.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 198:  Jan. 13 – Jan. 17
  • Daytime slide removal along Highway 198 from San Lorenzo Creek Bridge to Griffin Road between 8 a.m. and 3:30 p.m.
  • Motorists can expect delays of approximately 10 minutes.

Friday, January 3, 2014

ROAD AND LANE CLOSURES FOR JAN 5 - JAN 12


Here are the major scheduled road and lane closures for Monterey County from Sunday, January 5, through Sunday, January 12, 2013 – newest information is in red. Please keep in mind that construction work is weather-dependent.

Highway 1 – Near Lucia
  • Crews have completed the installation and activation of a temporary traffic signal on Highway 1 just north of Big Creek Bridge near Lucia.
  • This section of roadway will have signalized, reverse one-way traffic control 24/7 for the next several months.
  • Highway 1 will remain open during this traffic control for all motorists, cyclists, and local businesses.
  • Motorists can expect delays of approximately 10 minutes.
Highway 1 – Big Sur:  Jan. 6 – 10
  • Daytime drainage work along Highway 1 between Big Sur and Garrapata Creek Bridge from 8:30 a.m. to 3 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 101 – Greenfield:  Jan. 6 – 10
  • Daytime crack and seal work along northbound Highway 101 between Thorne Road and Arroyo Seco Road from 9 a.m. to 3 p.m.
  • Motorists can expect delays of approximately 5 minutes.
Highway 101 – Gonzales and Soledad:  Jan. 6 – Jan. 10
  • Daytime paving, drainage, and electrical work on Highway 101 from La Gloria Road to Arroyo Seco Road will result in alternating lane and ramp closures—northbound and southbound—between 4 a.m. and 4 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Prunedale Improvement Project: Jan. 6 – Jan. 10
  • Nighttime drainage work will result in alternating lane closures on northbound and southbound Highway 101 between Vierra Canyon Road and Tustin Road from 7:30 p.m. and 6 a.m.
  • Motorists can expect delays of approximately 10 minutes