Here are the major scheduled road and lane closures for Monterey County from Sunday, August 2 through Sunday, August 9,
2015 – newest information is in red. Please keep in mind that construction work is
weather-dependent.
Highway 1 – Gorda to Ragged Point: August 2 –
August 7
- A major retaining wall
construction project will result in daytime traffic control and full night
time closures of Highway 1 between Gorda and Ragged Point from 10 p.m. to
7 a.m.
- Night work will take place Sunday
nights through Friday mornings.
- Motorists traveling north/south
of these closures are advised to reach their destinations before 10 p.m.
- All local businesses along the
coast will remain open during the roadwork.
- Motorists should expect daytime delays of approximately 10 minutes.
Highway 101 – King City: August 3 –
August 7
- Daytime tree removal along
southbound Highway 101 between Central Avenue and Lagomarsino Avenue from
6 a.m. to 3 p.m.
- Motorists should expect daytime delays of approximately 10 minutes.
Highway 101 – San Juan Road: August
3 – August 7
- Night time construction work
along southbound and northbound Highway 101 between Dunbarton Road (South)
and Cannon Road/Rocks Road from 7:30 p.m. and 5:30 a.m.
- The southbound and northbound San
Juan Road Interchange ramps will be subject to closure.
- Motorists should expect delays of approximately 10 minutes.
River Road Overlay Project
- Daytime pavement work along River
Road between Parker Road and Chualar River Road from 7:30 a.m. to 5 p.m.,
Monday through Friday.
- Motorists are encouraged to seek
an alternate route.
- The project is currently scheduled
for completion by August 31.
- Motorists should expect delays of approximately 10 minutes.
Salinas: East Alisal Street/Skyway Boulevard
Roundabout Project
All
underground work has been completed.
Demolition for splitter island and bio-swales is 90% complete, and the
contractor, Anderson Pacific Engineering of Santa Clara, has started
reconstruction work (a 2+ week effort).
The project is on schedule for operational completion by the California
International Airshow in Salinas (September 26 and 27). Traffic detours around
the intersection are in effect.
Motorists should expect 5-10 minute delays.
Salinas: Sanborn Road Waterline
Project: Fairview Avenue – Eucalyptus Drive
In a continuing effort to improve water distribution to its
customers (with sufficient pressure and quantity), California Water Service
Company is undertaking several water main upgrades within the Salinas city
limits. One of the more significant upgrades is the upcoming installation
of a 12” water main within Sanborn Road that will extend from Fairview Avenue
to Eucalyptus Drive (roughly 1.1 miles long), constructed in phases beginning
at Fairview, and ending at Eucalyptus. Construction is expected to
commence the week of July 27 and take approximately 3 months to complete.
Traffic controls for lane closures will be in effect from 8 a.m. to 4 p.m.
daily. To lessen the impact on traffic work in the intersections of John
Street, E. Alisal street and E. Market Street will be done at night.
Motorists are encouraged to use alternate routes to destinations or
travel outside of the construction times. Motorists should expect delays
along the Sanborn Road corridor in the vicinity of work during
construction. The contractor for the project is West Valley Construction
Company. They have assured Cal water that all driveways to businesses in the
area will remain open during construction. California Water Service apologizes
for any inconvenience this project may cause and wants to thank the public for
their patience during the construction of this project.