Here are the major scheduled
road and lane closures for Monterey County from Sunday, June 9, through Sunday, June 16, 2013 – newest information is in
red.
Please
keep in mind that construction work is weather-dependent.
Highway 1 Closure at Pitkins
Curve Bridge And Rockshed: June 10
- Hwy 1 at Pitkins
Curve will be fully closed from midnight on Sunday, June 9, until 6
am on Monday, June 10.
- The full
six-hour early morning closure is necessary to remove a temporary working
platform near the rockshed.
- Motorists should
detour to Hwy. 68, U.S. Hwy. 101 to either Nacimiento-Fergusson Road or
Hwy. 46
Highway 1/Rocky Creek Viaduct Project: June 9
– June 14
- Daytime
roadwork on Highway 1 continues next week from 7 am to 5 pm Monday, June 10
through Friday, June 14
- There WILL be
NIGHT ROADWORK starting Sunday, June 9 through Thursday, June 13 (Friday
7am) from 9 pm to 7
am
- There will be NO
OVERNIGHT FULL closures next week
- Motorists can
expect delays of approximately 10 minutes
Highway 1 at Rocky Creek has
one-way signalized traffic control 24/7. Traffic will be stopped for 10 minutes
at a time during daytime roadwork.
Highway 1 through Big Sur: June
11 – June 14
- Day
time shoulder work and vegetation spaying continues along the Big Sur
coast between Lime Creek Bridge and Garrapata Creek Bridge.
- Motorists
can expect delays of approximately 10 minutes.
Highway 1 pavement work through
Big Sur: June 10 – June 14
- Caltrans will
conduct pavement and guardrail work at the following locations.
- Ventana
Entrance to 4 miles south;
- Little
Sur River Bridge to Hurricane Point;
- Garrapata
Ridge Road to Garrapata Creek Bridge; and
- Carmelite
Monastery to Point Lobos St Reserve.
- Motorists can
expect delays of approximately 10 minutes.
Highway 1/ Salinas Road to Watsonville: June 11 – June 13
- Daytime work on Highway 1, from
Salinas Road to the Santa Cruz County Line, will result in alternating
lane closures—northbound and southbound—between 7 a.m. and 4 p.m.
- Motorists can expect delays of
approximately 15 minutes.
Highway 101 between Salinas and Gonzales: June 10 – June 14
- Daytime work on Highway 101,
from Abbott St to Alta St, will result in alternating lane
closures—northbound and southbound—between 9 a.m. and 3 p.m.
- Crews will be sealing cracked
pavement.
- Motorists can
expect delays of approximately 10 minutes.
Prunedale
Improvement Project Ralph Lane - Pesante Road: June 10 – June 14
- Night work on Highway 101,
between Ralph Ln and at Pesante Rd, will result in alternating lane
closures (as needed) between 7:30 p.m. and 6 a.m.
- Motorists
can expect delays of approximately 10 minutes
Prunedale Improvement Project at Crazy Horse
Canyon: June 10 – June 14
- Night work continues between
Mallory Canyon Road and Echo Valley Road from Monday, June 10, to Friday,
June 14.
- There will be alternating lane closures
as needed between 7:30 p.m. and 6 a.m.
- There will be no left turns from Crazy Horse Canyon Rd
to Highway 101 South on Monday, June 10, between 7:30 p.m. and 6 a.m.
- Motorists
can expect delays of approximately 10 minutes.
- Crews will be moving equipment
and removing bridge falsework.
San Juan Road Interchange: June 9 – June 14
·
Overnight work on Hwy 101, between
Dunbarton Road and Cannon Road/Rocks Road, will result in lane closures between
the hours of 7:30 p.m. and 6 a.m.
·
Motorists can expect delays of
approximately 10 minutes
Highway 156 at Castroville Blvd: June 9
- Crews will repair guardrail on
Highway 156 near Castroville Blvd. on Sunday, June 9, between 7 a.m. and
10 a.m.
- Motorists can expect delays of approximately 8 minutes.
Blackie Road Safety Improvement Project: June 10 –
June 14
·
Roadway construction continues between
Borromeo Drive to approximately one mile west of Borromeo Drive going to
Castroville
·
Blackie Road will be open to emergency
vehicles, school buses, local residents and patrons of local businesses
·
Motorists can expect delays of
approximately 30 minutes.
###