Here are the major scheduled
road and lane closures for Monterey County from Sunday, June 23, through Sunday, June 30, 2013 – newest information is in
red.
Please
keep in mind that construction work is weather-dependent.
Highway 1/Rocky Creek Viaduct Project: June 24
– June 28
- Daytime
roadwork on Highway 1 continues next week from 7 am to 5 pm Monday, June 24
through Friday, June 28.
- There WILL be
NIGHT ROADWORK starting Sunday, June 23 through Thursday, June 27 (Friday
at 7am).
- There will be NO
OVERNIGHT FULL closures next week.
- Motorists can
expect delays of approximately 10 minutes.
Highway 1 at Rocky Creek has
one-way signalized traffic control 24/7. Traffic will be stopped for 10 minutes
at a time during daytime roadwork.
Highway 1
through Big Sur: June 24 – June 28
- Day
time work including vegetation spraying, paving, and replacing pavement
markers continues along the Big Sur coast between Lime Creek Bridge and Casa
Verde Way.
- Motorists
can expect delays of approximately 10 minutes.
Highway 101 Soledad:
June 24 – June 28
- Daytime bridge work on Arroyo
Seco Road at Highway 101 will result in surface street lane closures—eastbound
and westbound—between 8:30 a.m. and 3:30 p.m.
- Motorists can expect delays of approximately 10
minutes.
Highway 101 Gonzales and Chualar: June 24 – June 28
- Daytime work on Highway 101,
from Gloria Road to Chualar Road, will result in alternating lane
closures—northbound and southbound—between 7 a.m. and 3:30 p.m.
- Crews will be surveying, and sealing
cracked pavement.
- Motorists can expect delays of approximately 15
minutes.
Highway 101 – Boronda Road:
June 23
- Daytime work on the southbound
on-ramp to Highway 101 at Boronda Rd. will close one lane between 1 p.m.
and 4 p.m.
- Motorists can expect delays of approximately 5 minutes.
Highway 101 Salinas:
June 23 – June 28
- Nighttime bridge work on
Highway 101 at East Market St. will result in alternating lane closures
between 8 p.m. and 5 a.m.
- Daytime bridge work on Highway
101 at Sherwood Dr. will result in alternating lane closures between 8:30
a.m. and 3:30 p.m.
- Motorists can expect delays of approximately 10
minutes.
Prunedale Improvement Project – Espinosa Road: June 24 – June
28
- Daytime work on Espinosa Road near
Hwy 101 in Salinas will result in surface street lane closures (as needed)
between 8:30 a.m. and 3:30 p.m.
- Motorists
can expect delays of approximately 10 minutes.
Prunedale
Improvement Project – Ralph Lane - Pesante Road: June 24 – June 28
- Night work on Highway 101,
between Ralph Ln and Pesante Rd, will result in alternating lane closures (as
needed) between 7:30 p.m. and 6 a.m.
- Motorists
can expect delays of approximately 10 minutes.
Prunedale Improvement Project – Reese Circle: June 23
- Daytime work on northbound Highway
101 at Reese Circle will close one lane between 10 a.m. and 1 p.m.
- Motorists can expect delays of approximately 5 minutes.
Prunedale Improvement Project – San Miguel Canyon Road: June 23
- Daytime work on the northbound
on-ramo to Highway 101 at San Miguel Canyon Rd. will close one lane between
7 a.m. and 10 a.m.
- Crews will be repairing
guardrail.
- Motorists can expect delays of approximately 5 minutes.
San Juan Road Project – Dunbarton Road South: June 23 – June 28
- Night work on Highway 101,
between Dunbarton Rd. South and Rocks Rd. will result in single lane
closures between 7:30 p.m. and 6 a.m.
- Motorists can expect delays of approximately 5 minutes.
San Juan Road Project – San Juan Road: June 23 – June 28
- Daytime work on Highway 101 at
San Juan Road will result in alternating lane closures between 7 a.m. and 5 p.m.
- Motorists can expect delays of approximately 5 minutes.
Highway 183 at Tembladero Bridge: June 23 - 28
- Nighttime bridge work on
Highway 183 Tembladero Bridge will result in alternating lane closures
between 8 p.m. and 5 a.m.
- Motorists can expect delays of approximately 10
minutes.
Blackie Road Safety Improvement Project: June 24 –
June 28
- Roadway construction continues between Borromeo Drive to approximately one mile west of Borromeo Drive going to Castroville.
- Blackie Rd. will be open to emergency vehicles, school buses, local residents and patrons of local businesses.
- Motorists can expect delays of approximately 30 minutes.
***UPCOMING TEMPORARY CLOSURE: San Juan Road: July 1- 2***
- San Juan Road will be closed to through traffic just after the 76 Gas Station to Dunbarton Road from 7 a.m. to 5 p.m. on July 1 and July 2.
- Motorists should detour to Dunbarton Road.
- Motorists can expect delays of approximately 5 minutes.
###
No comments: