MONTEREY COUNTY – Here are the major scheduled road and lane closures for the areas between Salinas and North Monterey County from Sunday, April 28, through Sunday, May 5, 2013– newest information is in red. Please keep in mind that construction work is weather-dependent.

Highway 1 Big Sur Marathon April 28

  •  Highway 1 will be subject to full closure on Sunday, April 28 for the Big Sure Marathon.  

Highway 1/Rocky Creek Viaduct Project:  Apr 28  – May 3

  • Daytime roadwork on Highway 1 continues next week from 7 am to 5 pm Monday, April 29 through Friday, May 3. Traffic will be stopped for 10 minutes at a time during daytime roadwork.
  • There will be no night work or overnight closures next week—from Sunday, April 28 through Thursday, May 2.

Work next week will consist of grading the viaduct approaches.
Highway 1 at Rocky Creek has one-way signalized traffic control 24/7. Traffic will be stopped for 10 minutes at a time during daytime roadwork.

Highway 1/ Anderson Canyon Bridge:  Apr 29 – May 3

  • Crews will be repairing pavement between Anderson Canyon Bridge and Fullers Point between 8:30 a.m. and 3:00 p.m.
  •  Motorists can expect delays of approximately 10 minutes

Highway 1/ Del Monte Avenue:  May 1 – May 2

  • Daytime work will close the Del Monte off Ramp on Wednesday, May 1, and the Del Monte Avenue on Ramp on Thursday, May 2 between 9:00 a.m. and 3:00 p.m.
  • Crews will be conducting bridge work

Highway 68 Between Skyline Forest Drive and the Entrance to Community Hospital: April 30 – May 3

  • Paving continues on Highway 68 between Skyline Forest Drive and the entrance to Community Hospital between the hours of 9 a.m. and 1 p.m., from Tuesday, April 30, to Friday, May 3.
  • Motorists can expect delays of approximately 10 minutes

John St/Route 68 in Salinas: April 29 – May 3
  • Night work continues on the John Street off-ramps between 7 p.m. and 6 a.m.
  • Crews will be conducting curb, gutter, and sidewalk Work
  • Motorists can expect delays of approximately 10 minutes
Highway 101/East Market in Salinas: April 29 – May 3

  •  Night work on the East Market Street off-ramps between 7 p.m. and 6 a.m.
  • Crews will be conducting curb, gutter, and sidewalk work
  • Motorists can expect delays of approximately 10 minutes

San Juan Road Interchange – Rocks/Cannon Road to Dumbarton: April 29 – May 3

  •  Highway construction between the hours of 7:30 p.m. and 6 a.m., from Monday, April 29, to Friday, May 3.
  •  Motorists can expect delays of approximately 15 minutes.

Highway 183 in Castroville: April 29 – May 3

  • Daytime work on Highway 183 in Castroville between 8:00 a.m. and 4:00 p.m. from Monday, April 29, to Friday, May 3.
  • Crews will be conducting curb, gutter, sidewalk work, and electrical work
  • Motorists can expect delays of approximately 10 minutes