Road and lane closures for Jan. 27 - Feb. 3


Here are the major scheduled road and lane closures for the areas between Salinas and North Monterey County from Sunday, January 27, through Sunday, February 3, 2013– newest information is in red. Please keep in mind that construction work is weather-dependent.


Highway 101 Slope Repair North of Prunedale: Jan. 28 – March
·         Crews will make repairs to a ½  mile section of southbound Hwy. 101 between Rocks Road  and Cole Road near Prunedale starting next Monday, Jan. 28.
·         The #1 (fast) lane will be closed in the southbound direction until Friday, February 1.
·         Roadwork hours will be from 8 am to 2 pm.
·         Up to 10 minute delays are anticipated.
·         Both southbound lanes of Hwy. 101 will remain open during the week of February 4-10 for the Pebble Beach golf tournament.
·         Roadwork is expected to be completed by the end of March, weather permitting.


Highway 1/Rocky Creek Viaduct Project:  Jan. 27 – Feb 3
·         Daytime roadwork on Highway 1 continues next week from 7 am to 5 pm Monday, Jan. 28 through Friday, Feb. 1.
·         Overnight closures continue from 9pm to 7am Sunday, Jan. 27 through Thursday, Jan. 31 (opening Friday at 7am)
·         Hwy. 1 @ Rocky Creek has one-way has one-way signalized traffic control 24/7.
·         Traffic will be stopped for 10 minutes at a time during daytime roadwork.

Highway 1 @ Fremont:  Jan. 27 – Feb. 1
·         Night work on Hwy 1 at Fremont St. will result in closures between the hours of 7 p.m. – 6 a.m. from Sunday, January 27, to Friday, February 1.
·         Motorists can expect delays of approximately 10 minutes.
·         Crews will be working on the guardrail.

Highway 1 between Salinas Rd. and Route 129:  Jan. 28 – Jan. 31
·         Grinding on Hwy 1 near Watsonville, between Salinas Road and Route 129 will result in lane closures between the hours of 7:30 a.m. and 4 p.m. from Monday, January 28, to Thursday, January 31.
·         Motorists can expect delays of approximately 15 minutes.

Highway 68 @ Highway 1 (East):  Jan. 27 – Feb. 1
·         Night work on Hwy 68 at Hwy 1 (east) will result in closures between the hours of 7 p.m. – 6 a.m. from Sunday, January 27, to Friday, February 1.
·         Motorists can expect delays of approximately 10 minutes.
·         Crews will be working on the guardrail.

Prunedale Improvement Project – Crazy Horse Canyon Road: Jan 27 – Feb 3
  • Night work on Hwy 101 between Crazy Horse Canyon Road and Echo Valley Road will close lanes in each direction between 7:30 p.m. and 6 a.m. from Monday, January 28, to Friday, February 1.
  • Night work on Crazy Horse Canyon Road will result in flagging for both directions between 7:30 p.m. and 6:00 a.m. from Monday, January 28, to Friday, February 1.
  • Crews will be moving equipment and installing piles.



###

Thursday, January 17, 2013

Road and lane closures for Jan. 20 - 27


Here are the major scheduled road and lane closures for the areas between Salinas and North Monterey County from Sunday, January 20, through Sunday, January 27, 2013– newest information is in red. Please keep in mind that construction work is weather-dependent.


Highway 1/Rocky Creek Viaduct Project:  Jan. 20 – Jan. 27
·         Daytime roadwork on Highway 1 continues next week from 7 am to 5 pm Monday, Jan. 21 through Friday, Jan. 25
·         Overnight closures continue from Sunday, Jan. 20 through Thursday, Jan. 24 (opening Friday am).
·         Hwy. 1 @ Rocky Creek has one-way has one-way signalized traffic control 24/7.
·         Traffic will be stopped for 10 minutes at a time during daytime roadwork.

Highway 1 @ Fremont:  Jan. 20 – Jan. 25
·         Night work on Hwy 1 at Fremont St. will result in closures between the hours of 7 p.m. – 6 a.m. from Sunday, January 20, to Friday, January 25.
·         Motorists can expect delays of approximately 10 minutes.
·         Crews will be working on the guardrail.

Highway 68 @ Highway 1 (East):  Jan. 20 – Jan. 25
·         Night work on Hwy 68 at Hwy 1 (east) will result in closures between the hours of 7 p.m. – 6 a.m. from Sunday, January 20, to Friday, January 25.
·         Motorists can expect delays of approximately 10 minutes.
·         Crews will be working on the guardrail.

Prunedale Improvement Project  Location 2: Jan 21 – Jan 23
  • Night work on Hwy 101 between Ralph Road and Pesante Road will close lanes in each direction between 7:30 p.m. and 6:00 a.m. from Monday, January 21, to Wednesday, January 23.
  • Contractor will be moving temporary guardrail. 
Prunedale Improvement Project – Crazy Horse Canyon Road: Jan 21 – Jan 25
  • Night work on Hwy 101 between Crazy Horse Canyon Road and Echo Valley Road will close lanes in each direction between 7:30 p.m. and 6 a.m. from Monday, January 21, to Friday, January 25. 
San Juan Road Project: Jan. 22 – Jan. 24
  • Daytime work from Tuesday, January 22, through Thursday, January 24, will close one southbound lane on Highway 101 between Cole Road and San Juan Road.
    • Work hours are 10 a.m. to 2 p.m.

Friday, January 11, 2013

Road and lane closures for Jan. 13 - 20


Here are the major scheduled road and lane closures for the areas between Salinas and North Monterey County from Sunday, January 13, through Sunday, January 20, 2013– newest information is in red. Please keep in mind that construction work is weather-dependent.


Highway 1/Rocky Creek Viaduct Project:  Jan. 7 – Jan. 11
·         Daytime roadwork on Highway 1 continues next week from 7 am to 5 pm Monday, Jan. 14, through Friday, Jan. 18. 
·         Overnight closures continue from Sunday, Jan. 13 through Thursday, Jan. 17 (opening Friday am).
·         Hwy. 1 @ Rocky Creek has one-way has one-way signalized traffic control 24/7.
·         Traffic will be stopped for 10 minutes at a time during daytime roadwork.

Highway 1 @ Fremont:  Jan. 13 – Jan. 18
·         Night work on Hwy 1 at Fremont St. will result in closures between the hours of 7 p.m. – 6 a.m. from Sunday, January 13, to Friday, January 18.
·         Motorists can expect delays of approximately 10 minutes.
·         Crews will be working on the guardrail.

Highway 1 from Trafton Road to Airport Blvd: Jan 14 – Jan 17
  • Daytime work on Hwy 1, between Trafton Road and Airport Blvd., will close lanes in both directions between 8 a.m. and 4 p.m.
    • Motorists can expect delays of approximately 15 minutes.

Highway 68 @ Highway 1 (East):  Jan. 13 – Jan. 18
·         Night work on Hwy 68 at Hwy 1 (east) will result in closures between the hours of 7 p.m. – 6 a.m. from Sunday, January 13, to Friday, January 18.
·         Motorists can expect delays of approximately 10 minutes.
·         Crews will be working on the guardrail.

Highway 101 near East Market St.: Jan. 13 – Jan. 18
·         Night work on the Hwy 101 off ramp at East Market St. in Salinas, will result in closures between the hours of 7 p.m. and 5 a.m. from Sunday, January 13, to Friday, January 18.
·         Motorists can expect delays of approximately 10 minutes.

Prunedale Improvement Project  Location 2: Jan 14 – Jan 18
  • Night work on Hwy 101 near Blackie Road, Pesante Road and Reese Circle will close lanes in each direction between 7:30 p.m. and 6 a.m. from Monday, January 14, to Friday, January 18.
  • Contractor will be placing temporary guardrail in the median of Highway 101, preventing traffic on both north and south bound Highway 101 from making left turns at Blackie Road, Pesante Road, and Reese Circle.

Prunedale Improvement Project  Location 4: Jan 14 – Jan 18
  • Night work on Hwy 101 between Mallory Canyon Road and Echo Valley Road will close lanes in each direction between 8:30 p.m. and 5:30 a.m. from Monday, January 14, to Friday, January 18.
  • Contractor will be removing temporary guardrail.

Prunedale Improvement Project – Crazy Horse Canyon Road: Jan 14 – Jan 18
  • Night work on Hwy 101 between Crazy Horse Canyon Road and Echo Valley Road will close lanes in each direction between 7:30 p.m. and 6 a.m. from Monday, January 14, to Friday, January 18.

Prunedale Improvement Project – Crazy Horse Canyon Road: Jan 15
·         Daytime work on the Prunedale Improvement Project will temporarily close the US 101 northbound deceleration lane to Crazy Horse Canyon Road on Tuesday, January 15, between the hours of 6:30 a.m. and 3:30 p.m.
·         There is a detour available.
·         This temporary closure is to allow crews to safely pour concrete for the new overpass. This closure will be cancelled in the case of rain.
·         During this closure:
o    Emergency responders will be able to use the Crazy Horse Canyon exit.
o    All other traffic will access Crazy Horse Canyon Rd. via the following detour:
§  Exit Hwy 101 at Boronda Rd.
§  Head east on Boronda Rd. to San Juan Grade Road.
§  Turn left on San Juan Grade Road and follow it to Crazy Horse Canyon Road.
§  Turn left on Crazy Horse Canyon Road.
§  Please see map (below) for the detour route.






San Juan Road Project: Jan. 14 – Jan. 18
·         Night work from Monday, January 14, through Friday, January 18, will have crews working along Highway 101 between Dunbarton Road and Rocks Rd.
o    Work hours are 7:30 p.m. to 6 a.m.

  • Daytime work from Monday, January 14, through Thursday, January 17, will have crews working along Highway 101 between Dunbarton Road and San Juan Road.
    • Work hours are 10 a.m. to 2 p.m.

Celebrating a milestone: Prunedale South Road Overcrossing Ribbon Cutting Event!

TAMC celebrated the opening of the new Prunedale South Road over-crossing this morning! 

This is the first major section of the US 101/Prunedale Improvement Project to open to the public - thanks to all of our partners and stakeholders!

When it opens to traffic, on Monday, January 14, it will provide a safer way to get from one side of Highway 101 to the other. Northbound Highway 101 traffic will be able to cross over to Blackie Road and the west side of Highway 101 without having to make a left turn across southbound Highway 101 traffic, and vise-versa. 

Eliminating left turns across the highway will reduce the number of accidents and delays on US 101, providing much needed congestion relief for approximately 100,000 drivers every day.

Here are some photos from today's event:






















Monday, January 7, 2013

RECHEDULED!!! US 101 EXIT TO CRAZY HORSE CANYON RD. TEMPORARILY CLOSED ON JANUARY 15


 Detour to Crazy Horse Canyon is available via San Juan Grade Road

PLEASE NOTE: THIS CLOSURE HAS BEEN RESCHEDULED BY CALTRANS - NEW DATE: IS TUESDAY, JANUARY 15.

Caltrans work on the Prunedale Improvement Project will temporarily close the US 101 northbound deceleration lane to Crazy Horse Canyon Road on Tuesday, January 15, between the hours of 6:30 a.m. and 3:30 p.m. There is a detour available.

This temporary closure is to allow crews to safely pour concrete for the new overpass. This closure will be cancelled in the case of rain.

During this closure:
·         Emergency responders will be able to use the Crazy Horse Canyon exit.

·         All other traffic will access Crazy Horse Canyon Rd. via the following detour:
o   Exit Hwy 101 at Boronda Rd.
o   Head east on Boronda Rd. to San Juan Grade Road.
o   Turn left on San Juan Grade Road and follow it to Crazy Horse Canyon Road.
o   Turn left on Crazy Horse Canyon Road.
o   Please see map (below) for the detour route.


MAP OF CRAZY HORSE CANYON ROAD DETOUR FOR JANUARY 15, 2013


###

Friday, January 4, 2013

Road and lane closures for Jan 6 - 13


Here are the major scheduled road and lane closures for the areas between Salinas and North Monterey County from Sunday, January 6, through Sunday, January 13, 2013– newest information is in red. Please keep in mind that construction work is weather-dependent.


Highway 1/Rocky Creek Viaduct Project:  Jan. 7 – Jan. 11
·         Daytime roadwork on Highway 1 continues next week, from 7 am to 5 pm Monday, Jan. 7, through Friday, Jan. 11. 
·         Overnight closures continue from Sunday, Jan. 6 through Thursday, Jan. 10 (opening Friday am).
·         Hwy. 1 @ Rocky Creek has one-way has one-way signalized traffic control 24/7.
·         Traffic will be stopped for 10 minutes at a time during daytime roadwork.

Highway 1/Salinas River Bridge and Sand Dunes Drive: Jan. 9 – Jan. 10
·         Caltrans emergency striping project will close alternating lanes on Highway 1 in both directions
·         Work hours are from 8:30 am to 11:30 am on Wednesday, January 9, and Thursday, January 10.
·         Motorists can expect 15-minute delays.

Highway 1 @ Fremont:  Jan. 7 – Jan. 11
·         Night work on Hwy 1 at Fremont St. will result in closures between the hours of 7 p.m. – 6 a.m. from Monday, January 7, to Friday, January 11
·         Motorists can expect delays of approximately 10 minutes.
·         Crews will be working on the guardrail.

Highway 1 from Trafton Road to Airport Blvd: Jan 7 – Jan 11
  • Daytime work on Hwy 1, between Trafton Road and Airport Blvd., will close lanes in both directions between 8 a.m. and 4 p.m.
    • Motorists can expect delays of approximately 15 minutes.
 Highway 68 @ Highway 1 (East):  Jan. 6 – Jan. 11
·         Night work on westbound Hwy 68 between Griffin St. and John St. will result in closures between the hours of 7 p.m. – 5 a.m. from Sunday, January 6, to Friday, January 11.
·         Motorists can expect delays of approximately 10 minutes.


Highway 68 between Griffin St. and John St.: Jan. 6 – Jan. 11
·         Night work on Hwy 68 in Salinas, between Griffin St. and John St. will result in closures between the hours of 7 p.m. and 5 a.m. from Sunday, January 6, to Friday, January 11.
·         Motorists can expect delays of approximately 10 minutes.

San Juan Road Project: Jan. 7 – Jan. 10
·         Night work from Monday, January 7, through Thursday, January 10, will have crews working along Highway 101 between Dunbarton Road and Rocks Rd.
o    Work hours are 7:30 p.m. to 6 a.m.
o    Motorists can expect delays of up to 5 minutes.

San Juan Road Project – PG&E work: Jan. 10
·         PGE will be swapping some power lines next Thursday, January 10th, from one side of San Juan Road to the other.
·         They are going to have traffic control on San Juan Road and will have to detour people from the southbound 101 exit at San Juan Road to Dunbarton for some of this work.
·         The closure hours will be between 8am and 4pm.

Prunedale Improvement Project – Crazy Horse Canyon Rd: Jan 7 – Jan 11