Here are the major scheduled road and lane closures for Monterey County from Sunday, June 8, through Sunday, June 15, 2014 – newest information is in red. Please keep in mind that construction work is weather-dependent.

Highway 1 – Gorda to Lucia: June 10 – June 13
  • Daytime slide removal along Highway 1 between Gorda and Lucia from 8 a.m. to 3 p.m.
  • Motorists can expect delays of approximately 15 minutes.
Highway 1 – Big Sur Coast: June 9 – June 13
  • Daytime drainage work and vegetation spraying along Highway 1 between Lime Creek Bridge and Garrapata Creek Bridge from 8:45 a.m. to 3:15 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 1 – Big Sur Coast: June 4 – June 6
  • Daytime paving along Highway 1 between Juan Higuera Creek Bridge and Hurricane Point from 8:45 a.m. to 3:15 p.m.
  • Motorists can expect delays of approximately 10 minutes
Highway 1 – Marina: June 8 – June 13
  • Night time bridge work along southbound Highway 1 at the south Marina overcrossing from 9 p.m. to 6 a.m.
  • Motorists can expect delays of approximately 10 minutes
Highway 68 – Monterey: June 9 – June 13
  • Night time utility work on Highway 68 between Josselyn Canyon Road and Torero Drive from 8 p.m. to 5 a.m.
  • Motorists can expect delays of approximately 5 minutes.
Highway 101 – King City: June 9
  • Daytime bridge work along northbound Highway 101 between First Street and the San Lorenzo Creek Bridge from 9 a.m. and 3:30 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 101 – Soledad: June 12
  • Daytime guardrail repair along northbound Highway 101 between Highway 146 and Moranda Road from 9 a.m. and 3 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 101 – Salinas: June 10 – June 11
  • Daytime bridge work along southbound Highway 101 between Alisal Street and John Street from 9 a.m. and 3 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 101 – Prunedale Improvement Project: June 8 – June 13
  • Night work will result in alternating lane closures on northbound and southbound Highway 101 between Vierra Canyon Road and Crazy Horse Canyon Road from 7:30 p.m. and 6 a.m.
  • Motorists should expect delays of approximately 10 minutes.
Natividad Road – Salinas: June 9 – June 23
  • Utility work along Natividad Road between Laurel Drive and Alvin Drive will result in lane closures and minor delays.
  • 24-hour traffic control will be in effect from Tuesday, June 10 to Monday, June 23.
  • The closures are needed for a section of concrete paving to be replaced.
  • The work is part of a continuing gas line project in the area.
Blanco Road – Salinas to Marina: June 9 – June 29
  • Repairs start Monday on a portion of Blanco Road and last through June 29.
  • From Monday, June 9 through Thursday, June 19, crews plan to make repairs to the westbound lane of Blanco from Davis to Reservation roads.
    • A detour heading south along Davis Road to Reservation Road, then west on Reservation Road toward Marina, will be in place until crews are able to move into the eastbound lane.
  • From Monday, June 23 to Sunday, June 29, crews will be making repairs to the eastbound lane on the same portion of Blanco Road.
    • A detour on Reservation Road east, continuing past Blanco and turning onto Davis Road will be in place.
  • Work hours on this project will also be 9 a.m. to 4 p.m.
  • Motorists should expect delays of approximately 20 minutes.