Here are the major scheduled road and lane closures for Monterey County from Sunday, August 18, through Sunday, August 25, 2013 – newest information is in red. Please keep in mind that construction work is weather-dependent.
 
Highway 1/Rocky Creek Viaduct Project:  Aug. 19 – Aug. 23
  • Daytime roadwork on Highway 1 continues next week from 7 a.m. to 5 p.m. Monday, Aug. 19 through Friday, Aug. 23.
  • There will be NO OVERNIGHT CLOSURES OR NIGHT ROADWORK Sunday, Aug. 18 or Thursday, Aug. 22.
  • THERE WILL BE THREE OVERNIGHT FULL CLOSURES between 9 p.m. and 7 a.m. on:
    • Monday, Aug. 19,  
    • Tuesday, Aug. 20, and
    • Wednesday, Aug. 21.
  • Note: Wednesday night’s closure may not be necessary. An update will be sent as soon as confirmation is received either way.
Highway 1 at Rocky Creek has one-way signalized traffic control 24/7. Traffic will be stopped for 10 minutes at a time during daytime and nighttime roadwork.

Highway 1 Big Sur Coast:  Aug. 19 – 23
  • Daytime drainage, shoulder, and pavement work on Highway 1 between Hot Springs Creek Bridge and Garrapata Ridge Road from 8:30 a.m. to 3:15 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 68 – Reservation Road:  Aug. 18 – 23
  • Day and night time bridge work on Highway 68 at Reservation Road from 9 a.m. to 4 p.m. and 8 p.m. to 5 a.m. respectively.
  • Motorists can expect delays of approximately 10 minutes.
Highway 101 Greenfield and Soledad:  Aug. 19 – Aug. 23
  • Daytime bridge work on Highway 101 at three locations from 8:30 a.m. and 3:30 p.m.
    • Espinosa Road
    • Oak Avenue
    • Arroy Seco Road
  • Motorists can expect delays of approximately 10 minutes.
Highway 101 Gonzales and Soledad:  Aug. 19 – Aug. 23
  • Daytime drainage work on Highway 101 from La Gloria Road to Arroyo Seco Road will result in alternating lane closures—northbound and southbound—between 6 a.m. and 4 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 101 Gonzales:  Aug. 20 – Aug. 22
  • Daytime bridge work on Highway 101 at 5th Street from 8:30 a.m. and 3:30 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 101 Salinas:  Aug. 20 – Aug. 23
  • Night time bridge work on Highway 101 at Market Street from 9 p.m. and 11 p.m.;
  • And day time bridge work on Highway 101 at Sherwood Drive from 8:30 a.m. and 3:30 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Prunedale Improvement Project – Ralph Lane to Pesante Road:  Aug. 19 – Aug. 22
  • Nighttime work on Highway 101, from Ralph Lane to Pesante Road, will close one lane each direction between 7:30 p.m. and 6 a.m.
  • The closure is needed for crews to conduct work on the median barrier.
  • Motorists can expect delays of approximately 10 minutes.
San Juan Road Interchange — Crossover and Road Closure: Aug. 19 – Aug. 23
·        Temporary night time traffic crossover on Hwy. 101, between Dunbarton Road and Cole Road, starting Monday night, August 19 and going through Friday morning, August 23.
·        Night Work will also work will also temporarily close access to and from San Juan Road at Highway 101.
·        The crossover and road closure will occur between 7:30 p.m. and 6 a.m.
·        Motorists can expect delays of approximately 10 minutes.

Highway 146:  Aug. 19 – Aug. 22 
  • Daytime drainage work on Highway 146 from Stonewall Canyon Rd (West) to Ramus Road between the hours of 9 a.m. and 3 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 183:  Aug. 21 – Aug. 22 
  • Night time bridge work on Highway 183 at Tembladero Bridge between the hours of 9 p.m. and 5 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 198:  Aug. 19 – Aug. 22 
  • Daytime drainage work on Highway 198 East of San Lucas from 198 to the Fresno County Line between the hours of 8 a.m. to 3 p.m.
  • Motorists can expect delays of approximately 10 minutes.