Here
are the major scheduled road and
lane closures for Monterey County from Sunday,
August 18, through Sunday, August 25, 2013 – newest information is in red. Please keep in mind that construction work is weather-dependent.
Highway 1/Rocky Creek Viaduct Project: Aug. 19 – Aug. 23
- Daytime
roadwork on Highway 1 continues next week from 7 a.m. to 5 p.m. Monday, Aug.
19 through Friday, Aug. 23.
- There will be NO
OVERNIGHT CLOSURES OR NIGHT ROADWORK Sunday, Aug. 18 or Thursday, Aug. 22.
- THERE
WILL BE THREE OVERNIGHT FULL CLOSURES between 9 p.m. and 7 a.m. on:
- Monday,
Aug. 19,
- Tuesday,
Aug. 20, and
- Wednesday,
Aug. 21.
- Note: Wednesday night’s closure may not be necessary. An update will be sent as soon as confirmation is received either way.
Highway 1 at Rocky Creek has
one-way signalized traffic control 24/7. Traffic will be stopped for 10 minutes
at a time during daytime and nighttime roadwork.
Highway 1 Big Sur Coast: Aug. 19 – 23
- Daytime drainage, shoulder, and
pavement work on Highway 1 between
Hot Springs Creek Bridge and Garrapata Ridge Road from 8:30 a.m. to 3:15 p.m.
- Motorists can expect delays of approximately 10 minutes.
Highway 68 – Reservation Road: Aug. 18 – 23
- Day and night time bridge work
on Highway 68 at Reservation Road from 9 a.m. to 4 p.m. and 8 p.m. to 5 a.m.
respectively.
- Motorists can expect delays of approximately 10 minutes.
Highway 101 Greenfield and Soledad: Aug. 19 – Aug. 23
- Daytime bridge work on Highway
101 at three locations from 8:30 a.m. and 3:30 p.m.
- Espinosa Road
- Oak Avenue
- Arroy Seco Road
- Motorists can expect delays of approximately 10 minutes.
Highway 101 Gonzales and Soledad: Aug. 19 – Aug. 23
- Daytime drainage work on Highway
101 from La Gloria Road to Arroyo
Seco Road will result in alternating lane closures—northbound and southbound—between
6 a.m. and 4 p.m.
- Motorists can expect delays of approximately 10 minutes.
Highway 101 Gonzales: Aug. 20 – Aug. 22
- Daytime bridge work on Highway
101 at 5th Street from 8:30 a.m. and 3:30 p.m.
- Motorists can expect delays of approximately 10 minutes.
Highway 101 Salinas: Aug. 20 – Aug. 23
- Night time bridge work on
Highway 101 at Market Street from 9 p.m. and 11 p.m.;
- And day time bridge work on
Highway 101 at Sherwood Drive from 8:30 a.m. and 3:30 p.m.
- Motorists can expect delays of approximately 10 minutes.
Prunedale Improvement Project – Ralph Lane to Pesante
Road: Aug. 19 – Aug. 22
- Nighttime work on Highway 101,
from Ralph Lane to Pesante Road, will close one lane each direction between
7:30 p.m. and 6 a.m.
- The closure is needed for crews
to conduct work on the median barrier.
- Motorists can expect delays of approximately 10 minutes.
San Juan Road Interchange — Crossover and Road Closure: Aug. 19
– Aug. 23
· Temporary
night time traffic crossover on Hwy. 101, between Dunbarton Road and Cole Road,
starting Monday night, August 19 and going through Friday morning, August 23.
· Night Work will also work will also temporarily close access to and
from San Juan Road at Highway 101.
· The
crossover and road closure will occur between 7:30 p.m. and 6 a.m.
· Motorists
can expect delays of approximately 10 minutes.
Highway 146: Aug.
19 – Aug. 22
- Daytime drainage work on Highway
146 from Stonewall Canyon Rd (West) to Ramus
Road between the hours of 9 a.m. and 3 p.m.
- Motorists can expect delays of approximately 10 minutes.
Highway 183: Aug. 21 –
Aug. 22
- Night time bridge work on Highway
183 at Tembladero Bridge between the hours of 9 p.m. and 5 p.m.
- Motorists can expect delays of approximately 10 minutes.
Highway 198:
Aug. 19 – Aug. 22
- Daytime drainage work on Highway
198 East of San Lucas from 198
to the Fresno County Line between the hours of 8 a.m. to 3 p.m.
- Motorists can expect delays of approximately 10
minutes.
No comments: