Road and Lane Closures Feb 24 - Mar 3



Here are the major scheduled road and lane closures for the areas between Salinas and North Monterey County from Sunday, February 24, through Sunday, March 3, 2013– newest information is in red. Please keep in mind that construction work is weather-dependent.


Highway 1/Rocky Creek Viaduct Project:  Feb 25 – Mar 1

  • Daytime roadwork on Highway 1 continues next week from 7 am to 5 pm Monday, Feb.25 through Friday, March 1
  •  Overnight closures continue from 9pm to 7am Sunday, Feb. 24 and Monday, Feb. 25 and from 11pm to    7 am Tuesday, Feb. 26 through Thursday, Feb. 28 (opening Friday at 7am
  •   Highway. 1 @ Rocky Creek has one-way signalized traffic control 24/7.
  •   Traffic will be stopped for 10 minutes at a time during daytime roadwork.
  •   Construction continues with drilling to place falsework on bridge columns.

Highway 1/Big Sur Area: Maintenance Work: Feb 25 – Mar 1

  • Crews will be conducting tree work and shoulder work at multiple locations in the Big Sur vicinity.
  • Motorists can expect delays of approximately 10 minutes.

Highway 1 @ Fremont:  Feb 25 – Mar 1

  •  Night work on Highway 1 at Fremont St. will result in closures between the hours of 7 p.m. – 6 a.m. from Monday, February 25, to Friday, March 1.
  • Motorists can expect delays of approximately 10 minutes.


Highway 1/North of Moss Landing: Feb 26 – Mar 1

  • Crews will be conducting grinding operations at Springfield Road North of Moss Landing between the hours of 8 p.m. and 5 a.m.
  • Motorists can expect delays of approximately 15 minutes.

Highway 1/ Salinas Road to Watsonville:  Feb 25 – Mar 1

  • Daytime work on Highway 1, from Salinas Road to the Santa Cruz County Line, will result in alternating lane closures—northbound and southbound—between 7 am and 4 pm on Tuesday, February 25, to Friday, March 1.
  • Motorists can expect delays of approximately 15 minutes.


Highway 68 in Pacific Grove: Feb 26 – Feb 28

  •    Day work on Highway 68 between Morse Drive and Prescott Lane.
  •    Crews will be conducting pavement work between the hours of 8 a.m. and 4 p.m., from Tuesday, February 26, to        Thursday, February 28.
  •    Motorists can expect delays of approximately 10 minutes


Highway 68 between Highway 1 and Laguna Seca: Feb 25 – Mar 1

  • Night work on Highway 68 between Hwy 1 and Laguna Seca. Crews will be conducting drainage work between the hours of 7 p.m. and 6 a.m., from Monday, February 25, to Friday, March 1.
  •  Motorists can expect delays of approximately 10 minutes.

.
Prunedale Improvement Project – Crazy Horse Canyon Road: Feb 25 – Mar 1
  • Night work continues between Mallory Canyon Road and Echo Valley Road between 7:30 p.m. and 6 a.m. from Monday, February 25, to Friday, March 1.
  • Night continues at Crazy Horse Canyon Road between 7:30 p.m. and 6:00 a.m. from Monday, February 25, to Friday, March 1.
  • Crews will be conducting bridge work and pile driving.

South County: Highway 198 between Pine Valley Road and Griffin Road: Fed 25 – March 1.
­
  • Day time work. Crews will be removing a slide.
  • Motorists can expect delays of approximately 10 minutes