I will be out of the office tomorrow, so here’s the TAMC
Cone Zone Report a day early! Caltrans may have additional closure information
tomorrow; please check their website for the latest info! http://www.dot.ca.gov/dist05/road_information.htm
Community Outreach Coordinator
Transportation Agency for Monterey
County(TAMC)
Here are the major scheduled
road and lane closures for the areas between Salinas and North Monterey
County from Tuesday, September 4,
through Sunday, September 9, 2012– newest information is in red. Please keep in mind that construction work is
weather-dependent.
Prunedale Improvement Project:
Paving on N. Main/Russell/Harrison ending!
·
Granite Construction, Caltrans contractor for the Prunedale Improvement
Project, is expected to complete the paving along North Main, Russell, and
Harrison on September 4.
·
As the paving is going on
·
Harrison Rd., a portion of North Main St., and a
portion of Russell Rd. will still be considered to be construction zones;
·
Emergency response vehicles will have access at all
times;
·
Local traffic, including those going to businesses
in the area, will have access;
·
The speed limit in the construction
area will be reduced to 25 M.P.H.;
·
There will be traffic delays of up to 20 minutes –
especially along Harrison Rd.;
·
There will be construction noise
during the day, with crews generally working from 7 a.m. to 4 p.m.
Prunedale
Improvement Project: San Miguel Canyon Rd. and Hwy 101
·
Construction work on San Miguel
Canyon Rd., near Prunedale North Rd. and the Prunedale Shopping Center began on
Monday, June 25. This work involves
excavating the roadway to install new traffic signals, curbs, and sidewalks,
and rebuild the roadway.
o
Motorists can expect delays
of about 15 minutes in the area.
o
Work will be done during the day.
o
Businesses will be open, but access will change as work progresses.
Highway 68: July
30 - September
·
Caltrans began grinding and
paving a seven-mile section of Highway 68 from the Highway 1 interchange to SPCA
Road on Monday, July 30.
o
Roadwork will be done during overnight hours and is
expected to be completed this fall.
o
Roadwork hours
are Mondays through Thursdays from 7 pm to 6 am; Fridays from 1 a.m. to 6 a.m.,
and Sundays from 8 p.m. to midnight.
o
In areas where the roadway is four lanes, at least one
lane will remain open in each direction at all times.
o
Electronic
message signs will be posted.
o
Motorists can
expect 15-20 minute delays.
o
For more information on this project and for traffic
updates on other
Caltrans projects in Monterey County, residents can call the District 5 toll free number at 1-877-448-6771 or can visit Caltrans' website at http://www.dot.ca.gov/dist05/paffairs/release.htm
Caltrans projects in Monterey County, residents can call the District 5 toll free number at 1-877-448-6771 or can visit Caltrans' website at http://www.dot.ca.gov/dist05/paffairs/release.htm
###