Here
are the major scheduled road and
lane closures for Monterey County from Sunday,
August 23 through Sunday, August 30, 2015 – newest information is in red. Please keep in mind that construction work is
weather-dependent.
Highway 1 – Gorda to Ragged Point
- A major retaining wall
construction project will result in daytime traffic control and full night
time closures of Highway 1 between Gorda and Ragged Point from 10 p.m. to
7 a.m.
- Night work will take place Sunday
nights through Friday mornings.
- Motorists traveling north/south
of these closures are advised to reach their destinations before 10 p.m.
- All local businesses along the
coast will remain open during the roadwork.
- Motorists should
expect daytime delays of approximately 10 minutes.
Highway 1 – South of Lucia
- A ½-mile project to construct a
viaduct will result in one-way signalized traffic control, 24/7, 18 miles
south of Big Sur near Lucia from south of Big Creek Bridge to south of
Dolan Creek Bridge.
- All local businesses along the
coast will remain open during the roadwork.
- Motorists should
expect daytime delays of approximately 10 minutes.
Highway 1 – Monterey: August 24 –
August 27
- Daytime tree removal along
Highway 1 between Soledad Drive and the Iris Canyon Road from 9 a.m. to 2
p.m.
- Motorists should
expect daytime delays of approximately 5 minutes.
PG&E Gas Line Replacement Project –
Highway 68: August 27 – August 28
- Gas line replacement work will
result in night time lane closures along eastbound and westbound Highway
68 at Corral De Tierra Road from 8 p.m. to 5
a.m.
- Motorists can expect delays of
approximately 15 minutes
Highway 101 – Bradley to Salinas:
August 23 – August 28
- Daytime and night time bridge
work along Highway 101 between Jolon Road in Bradley and Alisal Street in
Salinas.
- Motorists should
expect daytime possible delays.
Highway 101 – King City: August 24 – August 28
- Daytime slab repair along northbound
Highway 101 between Wild Horse Road and First Street from 8 a.m. to 3:30
p.m.
- Motorists should expect daytime delays of approximately 10 minutes.
Highway 101 – King City: August 28
- Daytime guardrail repair along
southbound Highway 101 at Jolon Road from 8 a.m. to 3:30 p.m.
- Motorists should expect daytime delays of approximately 10 minutes.
Highway 101 – Greenfield: August 24
– August 28
- Daytime and night time pavement
work along northbound and southbound Highway 101 and ramps between
Espinosa Road and Walnut Avenue.
- Motorists
should expect delays of approximately 10 minutes.
Highway 101 – Salinas: August 26 – August
27
- Daytime survey work along Highway
101 between Airport Boulevard and North Main Street from 9 a.m. to 1 p.m.
- Motorists should expect daytime delays of approximately 5 minutes.
Salinas: East Alisal Street/Skyway Boulevard
Roundabout Project
The
City of Salinas is constructing its first modern Roundabout at the East
Alisal/Skyway intersection in Salinas.
Modern roundabouts generally provide the most efficient way of managing
traffic through an intersection, while providing the benefits of fewer conflict
points between pedestrians and motorists, which enhances pedestrian safety,
reduces congestion and average vehicle delay, generating less pollution (via
fewer vehicle stops and starts).
August
24 – August 28: concrete work for raised median and splitter islands.
Motorists should expect 5-10 minute
delays.
Salinas: Sanborn Road Waterline Project:
Fairview Avenue – Eucalyptus Drive
In
a continuing effort to improve water distribution to its customers (with
sufficient pressure and quantity), California Water Service Company is
undertaking several water main upgrades within the Salinas city limits.
One of the more significant upgrades is the upcoming installation of a 12”
water main within Sanborn Road that will extend from Fairview Avenue to
Eucalyptus Drive (roughly 1.1 miles long), constructed in phases beginning at
Fairview, and ending at Eucalyptus. Traffic controls for lane closures will be
in effect from 8 a.m. to 4 p.m. daily. To lessen the impact on traffic
work in the intersections of John Street, E. Alisal street and E. Market Street
will be done at night.
Motorists
are encouraged to use alternate routes to destinations or travel outside of the
construction times. Motorists should expect delays along the Sanborn Road
corridor in the vicinity of work during construction. The contractor for
the project is West Valley Construction Company. They have assured Cal water
that all driveways to businesses in the area will remain open during
construction. California Water Service apologizes for any inconvenience this
project may cause and wants to thank the public for their patience during the
construction of this project.