ROAD AND LANE CLOSURES FOR MAR 2 - MAR 9


Here are the major scheduled road and lane closures for Monterey County from Sunday, March 2, through Sunday, March 9, 2014 – newest information is in red. Please keep in mind that construction work is weather-dependent.

Highway 1 – Multiple Locations:  Mar. 3 – Mar. 7
  • Daytime drainage and pavement at multiple locations along Highway 1 between from 8 a.m. to 3:30 p.m.
  • Locations are:
    • Lime Creek Bridge to Garrapata Creek Bridge: Drainage work.
    • Hurricane Point to Garrapata Ridge Road: Crack and Seal work.
    • Rocky Creek Viaduct to Bixby Creek Bridge: Graffity Removal.
    • Rocky Creek Viaduct to Palo Colorado: Crack and Seal work.
  • Motorists can expect delays of approximately 10 minutes.
Highway 1 – Tree Removal at Multiple Locations:  Mar. 3 – Mar. 7
  • Four tree removal projects along southbound Highway 1 will take place Monday, March 3 through Friday, March 7 in the following locations:
  1. Southbound Hwy. 1, Mesa Drive/South Carmel Hill Drive near Carmel on:
·         Monday, March 3 and Tuesday, March 4 from 9 am to 3 pm.
·         Southbound traffic will be re-directed to northbound lane with delineation
·         Up to 30 minute delays are anticipated.

  1. Southbound Hwy. 1, Flanders Drive near Carmel on:
·         Wednesday, March 5 from 9 am to 3 pm.
·         Southbound traffic will be delineated to turn-pocket to get crane through
·         Up to 20 minute delays are anticipated.

  1. Southbound Hwy. 1,  Munras Off-ramp in Monterey on:
·         Thursday, March 6 from 9 am to 3 pm.
·         Southbound off-ramp will be closed at above location
·         Up to 5 minute delays are anticipated.

  1. Southbound Hwy. 1, Fern Canyon on:
·         Friday, March 7 from 9 am to 3 pm.
·         Southbound closure with one way traffic control on northbound lanes with flagging
·         Up to 10 minute delays are anticipated.

NOTE: There will be Electronic Message Boards alerting motorists and the CHP will assist with traffic control.

***SPECIAL NOTE: BIG SUR, CARMEL, CARMEL VALLEY AND CARMEL HIGHLANDS RESIDENTS TRAVELLING THIS AREA ARE STRONGLY ADVISED TO USE LAURELES GRADE.***

Highway 101 – Gonzales and Soledad:  Mar. 3 – Mar. 7
  • Daytime survey, median barrier, and striping work on Highway 101 from La Gloria Road to Arroyo Seco Road will result in alternating lane closures—northbound and southbound—between 4 a.m. and 4 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 101 – Prunedale Improvement Project: Mar. 3 – Mar. 7
  • Nighttime work will result in alternating lane closures on northbound and southbound Highway 101 between Vierra Canyon Road and Tustin Road from 7:30 p.m. and 6 a.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 101 – San Juan Road Interchange: Mar. 3 – Mar. 7
  • Night work on Highway 101 will cause alternating lane closures on northbound and southbound Highway 101 between Dunbarton Road and Rocks / Cannon Road from 7:30 p.m. and 6 a.m.
  • Motorists can expect delays of approximately 10 minutes.

Monday, February 24, 2014

HIGHWAY 101 LANE CLOSURE NEAR CRAZY HORSE CANYON ROAD TUESDAY FOR EMERGENCY EROSION CONTROL PROJECT

An emergency erosion control project will result in the closure of the No. 2 (slow) southbound lane of U.S. Highway 101 near Crazy Horse Canyon Road on Tuesday, Feb. 25 from 8 am to 12 noon.  Following this lane closure, the southbound shoulder of the highway will remain closed until 3 pm.

Motorists can expect a delay not to exceed 20 minutes.  This emergency erosion control project is necessary to maintain a safe condition for motorists with storms expected to move through the area next week.

Friday, February 21, 2014

ROAD AND LANE CLOSURES FOR FEB 23 - MAR 2


Highway 1 – Multiple Locations:  Feb. 24 – Feb 28
  • Daytime drainage and pavement at multiple locations along Highway 1 between from 8 a.m. to 3:30 p.m.
  • Locations are:
    • San Luis Obispo County Line to Soda Springs road: Crack and Seal work.
    • Lime Creek Bridge to Garrapata Creek Bridge: Drainage work.
    • Hurricane Point to Garrapata Ridge Road: Crack and Seal work.
  • Motorists can expect delays of approximately 10 minutes.
Highway 25:  Feb. 24 – Feb. 28
  • Daytime shoulder work on Highway 25 from Lonoak Road to Highway 198 between 8 a.m. and 3:30 p.m.
  • Motorists can expect delays of approximately 15 minutes.
Highway 68: Highway 1 to Ryan Ranch — Feb. 26
  • Daytime sweeping on Highway 68 from Highway 1 to Ryan Ranch between 9 a.m. and 2 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 68: Highway 1 Bridge — Feb. 25
  • Daytime bridge work on Highway 68 at Highway 1 between 9 a.m. and 12 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 101 – King City:  Feb. 25
  • Daytime guardrail work on the northbound and southbound Highway 101 on-ramps at First Street between 8 a.m. and 3:30 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 101 – Chualar:  Feb. 24
  • Daytime drainage work on northbound Highway 101 from Esperanza Road to Somavia Road between 9 a.m. and 3 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 101 – Salinas:  Feb. 24
  • Daytime striping on southbound Highway 101 off-ramp at Sanborn Road between 9 a.m. and 3 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 101 – Salinas:  Feb. 25 – Feb. 26
  • Daytime bridge work on northbound Highway 101 from Sanborn Road to John Street between 8 a.m. and 12 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Prunedale Improvement Project: Feb. 24 – Feb. 28
  • Nighttime work will result in alternating lane closures on northbound and southbound Highway 101 between Vierra Canyon Road and Tustin Road from 7:30 p.m. and 6 a.m.
  • Motorists can expect delays of approximately 10 minutes.
San Juan Road Interchange: Feb. 24 – Feb. 28
  • Night work on Highway 101 will cause alternating lane closures on northbound and southbound Highway 101 between Dunbarton Road and Rocks / Cannon Road from 7:30 p.m. and 6 a.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 198:  Feb. 24 – Feb. 28
  • Daytime shoulder work on Highway 198 from Freeman Flat Road to the Fresno County line between 8 a.m. and 3:30 p.m.
  • Motorists can expect delays of approximately 15 minutes.

Friday, February 14, 2014

ROAD AND LANE CLOSURES FOR FEB 16 - FEB 23


Here are the major scheduled road and lane closures for Monterey County from Sunday, February 16, through Sunday, February 23, 2014 – newest information is in red. Please keep in mind that construction work is weather-dependent.

Highway 1 – Multiple Locations:  Feb. 17 – Feb 21
  • Daytime drainage, pavement, and tree work at multiple locations along Highway 1 between from 8:30 a.m. to 3:30 p.m.
  • Locations are:
    • Lime Creek Bridge to Garrapata Creek Bridge: Drainage work.
    • Hurricane Point to Garrapata Ridge Road: Crack and Seal work.
    • Peter Pan Road: One-day tree work on Wednesday February 19.
    • Tioga Avenue to Sand Dunes Drive: one-day pavement repair on Tuesday February 18.
  • Motorists can expect delays of approximately 10 minutes.
Highway 101 – Gonzales and Soledad:  Feb. 18 – Feb. 21
  • Daytime survey, median barrier, and drainage work on Highway 101 from La Gloria Road to Arroyo Seco Road will result in alternating lane closures—northbound and southbound—between 4 a.m. and 4 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 101 – Chualar:  Feb. 19 – 21
  • Daytime drainage work on northbound Highway 101 from Esperanza Road to Somavia Road between 9 a.m. and 3 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Prunedale Improvement Project: Feb. 18 – Feb. 21
  • Nighttime work will result in alternating lane closures on northbound and southbound Highway 101 between Vierra Canyon Road and Crazy Horse Canyon Road from 7:30 p.m. and 6 a.m.
  • Motorists can expect delays of approximately 10 minutes.
San Juan Road Interchange: Feb. 18 – Feb. 21
  • Night work on Highway 101 will cause alternating lane closures on northbound and southbound Highway 101 between Dunbarton Road and Rocks / Cannon Road from 7:30 p.m. and 6 a.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 198:  Feb. 19 – 21
  • Daytime shoulder work on Highway 198 at Griffin Road between 8 a.m. and 3:30 p.m.
  • Motorists can expect delays of approximately 15 minutes.

Friday, February 7, 2014

ROAD AND LANE CLOSURES FOR FEB 9 - FEB 16


Here are the major scheduled road and lane closures for Monterey County from Sunday, February 9, through Sunday, February 16, 2014 – newest information is in red. Please keep in mind that construction work is weather-dependent.

Highway 1 – Multiple Locations:  Feb. 10 – Feb 14
  • Daytime drainage and tree work at multiple locations along Highway 1 between from 8:30 a.m. to 3:30 p.m.
  • Locations are:
    • Lime Creek Bridge to Garrapata Creek Bridge: Drainage work.
    • Hurricane Point to Garrapata Ridge Road: Crack and Seal work.
    • Peter Pan Road to Granite Canyon Bridge: Maintenance operation.
    • Carmel Valley Road to Moss Landing Road: Sweeping operation.
    • Iris Canyon Road, Aguajito Road, and Fremont Street: Guardrail repair.
  • Motorists can expect delays of approximately 10 minutes.
Highway 101 – Gonzales and Soledad:  Feb. 10 – Feb. 14
  • Daytime drainage and median work on Highway 101 from La Gloria Road to Arroyo Seco Road will result in alternating lane closures—northbound and southbound—between 4 a.m. and 4 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 101 – Chualar:  Feb. 11
  • Daytime drainage work on northbound Highway 101 from Esperanza Road to Somavia Road between 9 a.m. and 3 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 101 – Salinas:  Feb. 11 – Feb. 13
  • Daytime vegetation spraying on northbound Highway 101 from Airport Blvd to West Laurel Drive between 9 a.m. and 3 p.m.
  • Motorists can expect delays of approximately 5 minutes.
Prunedale Improvement Project: Feb. 10 – Feb. 14
  • Nighttime work will result in alternating lane closures on northbound and southbound Highway 101 between Vierra Canyon Road and Crazy Horse Canyon Road from 7:30 p.m. and 6 a.m.
  • Motorists can expect delays of approximately 10 minutes.
San Juan Road Interchange—Lane and ramp closures: Feb. 10 – Feb. 14
  • Night work on Highway 101 will cause alternating lane closures on northbound and southbound Highway 101 between Dunbarton Road and Rocks / Cannon Road from 7:30 p.m. and 6 a.m.
  • Night work will also temporarily close access to and from San Juan Road at Highway 101 between 8:30 pm and 5:30 am.
  • Motorists for San Juan Road should detour to San Miguel Canyon Road.
  • Motorists can expect delays of approximately 10 minutes.
Highway 156 – Prunedale and Castroville:  Feb. 13
  • Daytime vegetation spraying on Highway 156 from Highway 1 to Highway 101 between 10 a.m. and 2 p.m.
  • Motorists can expect delays of approximately 10 minutes.

Thursday, February 6, 2014

EMERGENCY STORM REPAIR TO TEMPORARILY CLOSE THE SOUTHBOUND 101 RIGHT (slow) LANE AT CRAZY HORSE CANYON ON FRIDAY, FEBRUARY 7


MONTEREY COUNTY – Caltrans will temporarily close the right (slow) lane of southbound Highway 101 at Crazy Horse Canyon between the hours of 9 a.m. and 12 p.m. on Friday, February 7. The Crazy Horse Canyon Interchange on-ramps and off-ramps will remain open during the lane closure.
The emergency closure is needed to fix a drain opening so rain water can safely flow from the Highway.

The closure and work are weather-dependent.