Here are the major scheduled road and lane closures for Monterey County from Sunday, November 3, through Sunday, November 10, 2013 – newest information is in red. Please keep in mind that construction work is weather-dependent.

Highway 1/Rocky Creek Viaduct Project:  Nov. 4 – Nov. 8  
  • Daytime roadwork on Highway 1 continues next week from 7 a.m. to 5 p.m. Monday, Nov. 4 through Thursday, Nov. 7.
  • There will be no overnight work or overnight closures scheduled from Sunday, Nov. 3 through Thursday, Nov. 7.
  • The temporary signal has been removed.
Traffic will be stopped for 10 minutes at a time during daytime roadwork.

Note: There will be no work on Monday, Nov. 11 in observance of the Veterans’ Day holiday.

Highway 1 – Big Sur Coast:  Nov. 4 – Nov. 8
  • Daytime drainage work along the Highway 1 between Lime Creek Bridge and Garrapata Creek Bridge from 8:45 a.m. to 3:30 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 1 – Monterey:  Nov. 7
  • One-day pavement marker replacement on northbound Highway 1 at Casa Verde Way from 9 a.m. to 1 p.m.
  • Motorists can expect delays of approximately 5 minutes.     
Highway 1 – Seaside:  Nov. 7
  • Bridge work on northbound Highway 1 at Route 218 from 9 a.m. to 2 p.m.
  • Motorists can expect delays of approximately 10 minutes.     
Highway 68 – Monterey:  Nov. 7
  • One-day striping operation on the westbound Highway 68 off-ramp between Fairgrounds Road and Highway 1 from9 a.m. 7- 2 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 101 – Gonzales and Soledad:  Nov. 3 – Nov. 8
  • Daytime paving, drainage, and electrical work on Highway 101 from La Gloria Road to Arroyo Seco Road will result in alternating lane closures—northbound and southbound—between 4 a.m. and 4 p.m.
  • Night time paving and survey work on Highway 101 from La Gloria Road to Arroyo Seco Road will result in alternating lane closures—northbound and southbound—between 6 p.m. and 5 a.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 101 – Salinas:  Nov. 4 – Nov. 8
  • Daytime crack and seal work on southbound Highway 101 between Airport Blvd and Gould Road from 9 a.m. to 3 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 101 – Salinas:  Nov. 4 – Nov. 6
  • Daytime paving and electrical work on the Highway 101 Market Street off-ramp from 7 a.m. to 5 p.m.
  • Motorists should detour to the John Street off-ramp.
  • Motorists can expect delays of approximately 10 minutes.
Prunedale Improvement Project – Multiple Locations:  Nov. 4 – Nov. 8
  • Nighttime work on Highway 101 in Prunedale will result in alternating lane closures—northbound and southbound—between 7:30 p.m. and 6 a.m.
    • Locations are:
      • Vierra Canyon Road to San Miguel Canyon Road for Miscellaneous work.
      • Messick Road to Crazy Horse Canyon Road for Median Barrier work.
  • Motorists can expect delays of approximately 10 minutes.
Prunedale Improvement Project – Espinosa Road:  Nov. 4 – Nov. 6
  • Daytime construction work on Espinosa Road will result will cause one way reversing traffic control between 7:30 a.m. and 3:30 p.m.
  • Motorists can expect delays in both directions of Espinosa Road, and are advised to take alternate routes, if possible.