Road and lane closures for March 10 - 17


Here are the major scheduled road and lane closures for the areas between Salinas and North Monterey County from Sunday, March 10, through Sunday, March 17, 2013– newest information is in red. Please keep in mind that construction work is weather-dependent.


Highway 1/Rocky Creek Viaduct Project:  Mar 10 – Mar 14

·         Daytime roadwork on Highway 1 continues next week from 7 am to 5 pm Monday, March 11 through Friday, March 15
·         Sunday, March 10 through Thursday, March 14—9 pm to 11 pm with up to 10-minute delays;
·         Sunday, March 10 through Thursday, March 14—11 pm to 7 am (Friday am) with up to 30-minute delays;
·         (Roadway will remain OPEN each night next week—no overnight hard closures)

·         Traffic will be stopped for 10 minutes at a time during daytime roadwork.
·         Completion is scheduled by Labor Day, weather permitting. Daily roadwork schedules are subject to change due to weather conditions and other factors so stay tuned for regular updates

Highway 1 @ Fremont:  Mar 10 – Mar 15
·         Night work on Highway 1 at Fremont St. will result in closures between the hours of 7 p.m. – 6 a.m. from Sunday, March 410, to Friday, March 15.
·         Motorists can expect delays of approximately 10 minutes.


Highway 1/North of Moss Landing: Mar 10 – Mar 15
  • Crews will be conducting grinding operations at Springfield Road North of Moss Landing between the hours of 8 p.m. and 5 a.m.
  • Motorists can expect delays of approximately 15 minutes.

Highway 1/ Salinas Road to Watsonville:  Mar 11 – Mar 15
·         Daytime work on Highway 1, from Salinas Road to the Santa Cruz County Line, will result in alternating lane closures—northbound and southbound—between 7 am and 4 pm on Monday, March 11, to Friday, March 15.
·         Motorists can expect delays of approximately 15 minutes.

Highway 68 between Highway 1 and Laguna Seca: Mar 10 – Mar 15

·         Night work on Highway 68 between Hwy 1 and Laguna Seca. Crews will be conducting drainage work between the hours of 7 p.m. and 6 a.m., from Sunday, March 10, to Friday, March 15.
·         Motorists can expect delays of approximately 10 minutes.

Prunedale Improvement Project: Mar 11 – Mar 15
  • Crews will be paving San Miguel Canyon Road and the southbound HWY 101 San Miguel Canyon Road off-ramp from Monday, March 11, through Friday, March 15.
    • Work hours will be 7:30 PM to 6 AM
    • This work WILL CLOSE the off-ramp from Southbound HWY 101 to San Miguel Canyon Road between the hours of 7:30 PM and 6 AM

  • Night work continues between Mallory Canyon Road and Echo Valley Road between 7:30 p.m. and 6 a.m. from Monday, March 11, to Friday, March 15.

  • Night work continues at Crazy Horse Canyon Road between 7:30 p.m. and 6:00 a.m. from Monday, March 11, to Friday, March 15.
    • Crews will be moving equipment and conducting bridge work.



###