Here
are the major scheduled road and
lane closures for the areas between Salinas and North Monterey County from Sunday, December 2, through Sunday,
December 9, 2012– newest information is in red. Please keep in mind that construction work is weather-dependent.
San Juan Road Project: Dec. 3 –
Dec. 7
· On
Monday, Dec. 3, construction will begin for the US 101 – San Juan Road
Interchange Project.
·
The $91 million project will significantly reduce congestion
and increase safety on the section of Highway 101 between Dunbarton Road in
Monterey County and Cole Road in San Benito County by removing three major
at-grade intersections (San Juan Road, Dunbarton Road and Cole Road) and
replacing them with a single interchange near the Red Barn at San Juan Road and
Route 101.
·
Daytime
work between Dec. 3 and Dec. 7 will have crews working along the shoulders
between Dunbarton Road and Rocks Rd.
Prunedale Improvement Project:
Dec. 3
· Night
work on Hwy 101 between Vierra Canyon Road and Messick Road will close one lane
between the hours of 7:30 p.m. and 6 a.m.
Highway 1/Rocky Creek Viaduct
Project: Dec. 2 – Dec. 7
·
Daytime roadwork continues from 7am to 5 pm
Monday, Dec. 3 through Friday, Dec. 7.
·
Overnight
closures of Highway 1 at Rocky Creek (Mile Marker 59.5), between Big Sur and
Carmel are scheduled for four nights beginning Sunday, Dec. 2 through Thursday,
Dec. 6 from 9 pm to 7 am.
·
Hwy.
1 @ Rocky Creek has one-way has one-way signalized traffic control 24/7.
Traffic will be stopped for 10 minutes at a time during daytime roadwork.
·
In order to minimize traffic impact as part of the
project, there will be advance notification for motorists, residents and
businesses via a traffic hotline, electronic message signs and email updates.
Highway 1 @ Carmel River Bridge: Dec. 5 – Dec. 7
·
Daytime
work on Hwy 1, between the Carmel River Bridge and Oliver Road, will close one
lane between the hours of 8:30 a.m. – 3:30 p.m. from Wednesday, December 5, to
Friday, December 7.
·
Motorists
can expect delays of approximately 5 minutes.
Highway 1 @ Fremont: Dec. 3 – Dec. 7
·
Night
work on northbound Hwy 1 at Fremont St. will result in closures between the
hours of 7 p.m. – 6 a.m. from Monday, December 3, to Friday, December 7.
·
Motorists
can expect delays of approximately 10 minutes.
·
Crews will be working on the guardrail.
Highway 68 @ Highway 1 (East): Dec. 2 – Dec 7
·
Night
work on westbound Hwy 68 at Hwy 1 (east) will result in closures between the
hours of 7 p.m. – 6 a.m. from Sunday, December 2, to Thursday, December 6.
·
Motorists
can expect delays of approximately 10 minutes.
·
Crews will be working on the guardrail.
Prunedale
Improvement Project: San Miguel Canyon Rd. and Hwy 101
- Construction work on San Miguel
Canyon Rd., near Prunedale North Rd. and the Prunedale Shopping Center,
began on Monday, June 25. This work
involves excavating the roadway to install new traffic signals, curbs and
sidewalks, and rebuild the roadway.
o
Motorists can expect delays
of about 15 minutes in the area.
o
Work will be done during the day.
o
Businesses are open, but access will change as work progresses.
###