Here are the major scheduled
road and lane closures for the areas between Salinas and North Monterey
County from Sunday, October 21, through
Sunday, October 28, 2012– newest information is in red. Please keep in mind that construction work is
weather-dependent.
Highway
101 in Salinas: Oct. 21 – Oct. 24
·
A three-night concrete slab replacement project on
a ¼ mile section of northbound Highway 101, between Airport Blvd and Sanborn
Road, will take place beginning at 6 p.m. on Sunday, Oct. 21.
o
Overnight roadwork hours will be from 6 pm to 6 am
each night. Closures are as follows:
§ The
northbound on-ramp from Fairview Ave. to Hwy. 101
§ The
northbound Sanborn Road off-ramp
§ The
northbound #2 (slow) lane between both
locations
·
Roadwork consists of
replacing deteriorated concrete sections with new ones through this stretch of
the highway. Work is expected to be completed by 6 am on Wednesday, Oct. 24.
Highway 1/Rocky Creek Viaduct
Project: Overnight Closures begin Oct. 22!
·
Daytime roadwork on Hwy 1 continues from dawn
until dusk next week.
·
Overnight
closures of Highway 1 at Rocky Creek (Mile Marker 59.5) are scheduled to begin
for four nights from Monday, Oct. 22, through Thursday, Oct. 25, from 9 pm to 7
am each night.
o
Construction continues with drilling work for the
viaduct columns.
o
Hwy.
1 @ Rocky Creek has one-way has one-way signalized traffic control 24/7. Traffic
will be stopped for 10 minutes at a time during daytime roadwork.
o
However, full overnight closures will be scheduled
five nights a week Sundays through Thursdays until February.
o
No full closures will occur on Friday/Saturday
nights.
·
At this time, no overnight closures are scheduled
for Wednesday, Oct. 31 or Thursday, Nov. 1 due to local events.
·
In order to minimize traffic impact as part of the
project, there will be advance notification for motorists, residents and businesses
via a traffic hotline, electronic message signs and email updates.
Prunedale
Improvement Project: San Miguel Canyon Rd. and Hwy 101
- Construction work on San Miguel
Canyon Rd., near Prunedale North Rd. and the Prunedale Shopping Center,
began on Monday, June 25. This work
involves excavating the roadway to install new traffic signals, curbs and
sidewalks, and rebuild the roadway.
o
Motorists can expect delays
of about 15 minutes in the area.
o
Work will be done during the day.
o
Businesses are open, but access will change as work progresses.
Traffic Advisories
from Monterey County Public Works
·
On Monday, October 15, Granite Construction, Monterey County
Public Works’ contractor for the Blackie Road Safety Improvements Project, will
temporarily close Blackie Road, from Borromeo Drive to a half a mile west of
Moro Terrace, between the hours of 8:30 a.m. and 3:30 p.m., Mondays through
Fridays, for approximately three weeks to all but local traffic and emergency
response vehicles.
o
Construction is scheduled to start on October 15 and go
through November 2; during this time:
§ All businesses
and places of worship in this area along Blackie Rd. will remain open;
§ Emergency
response vehicles will have access at all times;
§ Local traffic,
including those going to businesses in the area, will have access;
§ The speed limit in the construction area will be reduced to
25 M.P.H.;
§ Motorists can expect traffic delays of up to 30 minutes;
§ There will be construction noise during the day, with crews
working from 8:30 a.m. to 3:30 p.m.
o
This closure is necessary to safely
remove trees along Blackie Road. It is the first step of the $1.5 million
Blackie Road Safety Improvements Project, which will widen, add shoulders, and
repave Blackie Road.
###