ROAD AND LANE CLOSURES SCHEDULED FOR OCT 2 - OCT 9

Here are the major scheduled road and lane closures for the areas between Salinas and North Monterey County from Sunday, October 2, through Sunday, October 9 - newest information is in red.

Highway 68 through Downtown Salinas: Begins October 2
·         The five-mile project to overlay Hwy. 68 from River Road to Work Street in Salinas will begin Sunday night, October 2.
o    The work starting October 2 will take place between 6 pm and 7 am.
o    Up to 10-minute delays are anticipated with the daytime closures. 
o    This project goes through downtown Salinas.
o    There will be reduced or no parking in this construction zone due to micro-surfacing of the pavement.


Night work on Highway 1 to Highway 68: October 2 – October 7
·         Caltrans will close the Hwy 1 off ramp to Hwy 68 eastbound AND the westbound Hwy 68 connector to southbound Hwy 1 overnight from Sunday, September 25, through Thursday, September 29.
o   This closure will only be at night, between the hours of 8 p.m. and 5 a.m.
o    There will be a detour to southbound Hwy 1 via the Casa Verde off ramp.


Prunedale Improvement Project: October 2 – October 9
·         PG&E will close one lane on Echo Valley Road from Hwy 101 to Tustin Rd on Tuesday, October 4, from 7:00 am to 4:00 pm to finished pole relocation.
o    Traffic heading toward Hwy 101 will be detoured to Tustin Rd,
o    Traffic from Hwy 101 will be allowed through.
  

  • Night work from Monday, Oct. 3 – Thursday, Oct. 6, on HWY 101 at Russell and Espinosa between the hours of 7:30 p.m. and 6 a.m. will close:
    • The left turn to Espinosa Rd from the northbound Hwy 101
    • The right turn to Russell Rd from northbound Hwy 101
    • The right turn to Espinosa Rd from southbound Hwy 101
    • Emergency responders will have access at all times.

  • Night work on HWY 101 at San Miguel Canyon on Monday, Oct. 3 – Thursday, Oct. 7 will close the following between the hours of 7:30 p.m. and 6 a.m.:
    • One northbound lane between Tustin and San Miguel Canyon
    • The northbound on ramp at San Miguel Canyon
    • The northbound off ramp at San Miguel Canyon


·         Blackie Road remains closed from Highway 101 to Borromeo Drive for approximately two months.
o    During construction there will be no entrance to Blackie Road from either Highway 101 or Prunedale South Road.  (Please see graphic at the end of this news release.)
o    Blackie Road at Prunedale South Road will be closed to all but emergency response vehicles. 
o    The closure is necessary to install a new box culvert that will go underneath Blackie Rd.
o    More information about this closure is available at http://www.tamcmonterey.org


·         The Northbound HWY 101 on and off ramps at Russell/Espinosa will be closed between the hours of 8:30 a.m. and 3:30 p.m. until late September/early October, 2011.
o    Crews will be:
§  Widening and reconstructing North Main St. from Russell Rd to 1000 feet south of the Russell Rd/Main St. intersection;
§  Working on storm drainage systems and a traffic signal; and
§  Making improvements along Russell Rd. and Harrison Rd.
o    Work hours for this project will be from 8:30 a.m. – 3:30 p.m., Monday through Friday.
o    Flaggers will be in the area to direct traffic.


·         Cross Rd. in Prunedale is closed to through traffic for approximately six months; the road is open to residents and emergency responders.
o    Caltrans is removing the pavement, installing several new box culverts, and making improvements along Cross Rd. and Reese Circle.
o    Throughout this construction Cross Rd will be open for residents, but will be closed to through traffic.
o    Detour signs will be posted throughout the area.
o    During this period Granite Construction crews will be working from 7 a.m. to 3:30 p.m., Mondays through Fridays.

Highway 68: October 2 – October 9
·         Monterey County Public Works continues its work along HWY 68 and San Benancio, which will go on until December 2011. This work is being done during the day; drivers should be alert. Most work will be done behind the concrete barriers that are set up, but minor delays can be expected.



Special Events
·         Santa Cruz AIDS Project Bike Ride – October 2
    • On Sunday, Oct. 2, the Santa Cruz AIDS Project charity ride will begin at the Santa Cruz County line, and enter various North County roads.  
    • This will result in rolling closures along: McGowan Rd, Trafton Rd, Salinas Rd, Elkhorn Rd, Castroville Blvd, Collins Rd, Benson Rd, Pajaro St, Haro St, Cooper Rd, San Jon Rd, Boronda Rd, San Juan Grade Rd, various Aromas streets, and Murphy Rd. between 9am and 11am.
    • CHP will provide traffic control.
    • Details about routes and times at http://www.scapsite.org/ride.php

  • Rancho Cielo Youth 5K & 10K Run – October 8
    • Run will begin at 8:55 a.m. and end at 11 a.m.
    • Route follows Old Stage Road, Natividad Road, Old Natividad Road then back to Rancho Cielo. 
    • This event will require temporary road closures.
    • CHP will provide necessary traffic control, and proper signing will be installed throughout the course.

Please drive safely and exercise caution in the construction zones.
                                                                                   

###

Wednesday, September 28, 2011

DETOUR FOR SOUTHBOUND HIGHWAY 101 TRAFFIC IN NORTH SALINAS SCHEDULED TO BEGIN SEPTEMBER 29

 Shift will make room for construction of new lanes on 101 as Prunedale Improvement Project moves forward



MONTEREY COUNTY – Traffic patterns on Highway 101 in north Salinas will change the evening of September 29, when a new detour road paralleling Highway 101 will open for southbound traffic.

The detour will start a quarter mile south of Ralph Lane; southbound 101 traffic will shift on to the new road, then move back on to Highway 101 at Boronda Road.

The detour, which is part of the construction of the Prunedale Improvement Project, will move traffic away from the area where the new Sala Road overcrossing will be built.

Northbound traffic will stay on the regular northbound lanes of Hwy 101.

This is the first phase of detours for the Prunedale Improvement Project; a second is scheduled to begin October 12, when the northbound Hwy 101 traffic will move on to the detour.

Both detours will be in place for approximately one year, while the new Sala Road overcrossing and northbound Hwy 101 lanes are constructed.

All detour durations are subject to construction progress.

The Prunedale Improvement Project addresses traffic safety issues along Highway 101, from Espinosa/Russell Roads in Salinas north to Crazy Horse Canyon/Echo Valley Roads. The project includes construction of three new interchanges /overpasses and a continuous median barrier from Crazy Horse Canyon to Russell/Espinosa. These safety measures will eliminate left turns across Hwy 101, reduce delays on US 101, provide safer access for local business and residents and provide congestion relief for the thousands of vehicles that travel through the corridor every day.

Thursday, September 22, 2011

ROAD AND LANE CLOSURES SCHEDULED FOR SEP 25 - OCT 2

Here are the major scheduled road and lane closures for the areas between Salinas and North Monterey County from Sunday, September 25 through Sunday, October 2 - newest information is in red.

Highway 68 through Downtown Salinas: Delayed until Oct. 3
·          The five-mile project to overlay Hwy. 68 from River Road to Work Street in Salinas has been rescheduled to begin Monday, October 3.
o    Work will consist of daytime lane and ramp closures from 8:30 am to 4 pm, Mondays through Thursdays; and from 8:30 am to 1 pm on Fridays.
o    Overnight work may also take place between 6 pm and 7 am during the week.
o    Up to 10-minute delays are anticipated with the daytime closures. 
o    This project goes through downtown Salinas.
o    There will be reduced or no parking in this construction zone due to micro-surfacing of the pavement.


Night work on Highway 1 to Highway 68: September 25 - 29
·         Caltrans will close the Hwy 1 off ramp to Hwy 68 eastbound AND the westbound Hwy 68 connector to southbound Hwy 1 overnight from Sunday, September 25, through Thursday, September 29.
o   This closure will only be at night, between the hours of 8 p.m. and 5 a.m.
o    There will be a detour to southbound Hwy 1 via the Casa Verde off ramp.


Prunedale Improvement Project: September 25 – October 2
·         Caltrans will move southbound HWY 101 traffic on to the new southbound HWY 101 detour on Thuesday, September 29.
o    The move will happen after 7:30 p.m.
o    Travelers on southbound HWY 101 may experience some delays 
o    CHP will be on duty to assist with the move.


  • Night work from Monday, Sept. 26 – Thursday, Sept. 29, on HWY 101 at Russell and Espinosa between the hours of 7:30 p.m. and 6 a.m. will close:
    • The left turn to Espinosa Rd from the northbound Hwy 101
    • The right turn to Russell Rd from northbound Hwy 101
    • The right turn to Espinosa Rd from southbound Hwy 101
    • Emergency responders will have access at all times.

  • Night work on HWY 101 at San Miguel Canyon on Monday, Sept. 26 – Thursday, Sept. 29 will close the following between the hours of 7:30 p.m. and 6 a.m.:
    • One northbound lane between Tustin and San Miguel Canyon
    • The northbound on ramp at San Miguel Canyon
    • The northbound off ramp at San Miguel Canyon


·         Blackie Road remains closed from Highway 101 to Borromeo Drive for approximately two months.
o    During construction there will be no entrance to Blackie Road from either Highway 101 or Prunedale South Road.  (Please see graphic at the end of this news release.)
o    Blackie Road at Prunedale South Road will be closed to all but emergency response vehicles. 
o    The closure is necessary to install a new box culvert that will go underneath Blackie Rd.
o    More information about this closure is available at http://www.tamcmonterey.org


·         The Northbound HWY 101 on and off ramps at Russell/Espinosa will be closed between the hours of 8:30 a.m. and 3:30 p.m. until late September/early October, 2011.
o    Crews will be:
§  Widening and reconstructing North Main St. from Russell Rd to 1000 feet south of the Russell Rd/Main St. intersection;
§  Working on storm drainage systems and a traffic signal; and
§  Making improvements along Russell Rd. and Harrison Rd.
o    Work hours for this project will be from 8:30 a.m. – 3:30 p.m., Monday through Friday.
o    Flaggers will be in the area to direct traffic.


·         Cross Rd. in Prunedale is closed to through traffic for approximately six months; the road is open to residents and emergency responders.
o    Caltrans is removing the pavement, installing several new box culverts, and making improvements along Cross Rd. and Reese Circle.
o    Throughout this construction Cross Rd will be open for residents, but will be closed to through traffic.
o    Detour signs will be posted throughout the area.
o    During this period Granite Construction crews will be working from 7 a.m. to 3:30 p.m., Mondays through Fridays.

Highway 68: September 18 – September 25
·         Monterey County Public Works continues its work along HWY 68 and San Benancio, which will go on until December 2011. This work is being done during the day; drivers should be alert. Most work will be done behind the concrete barriers that are set up, but minor delays can be expected.



Special Event: Santa Cruz AIDS Project Bike Ride – October 2
·         On Sunday, Oct. 2, the Santa Cruz AIDS Project charity ride will begin at the Santa Cruz County line, and enter various North County roads. 
·         This will result in rolling closures along: McGowan Rd, Trafton Rd, Salinas Rd, Elkhorn Rd, Castroville Blvd, Collins Rd, Benson Rd, Pajaro St, Haro St, Cooper Rd, San Jon Rd, Boronda Rd, San Juan Grade Rd, various Aromas streets, and Murphy Rd. between 9am and 11am.
·         CHP will provide traffic control.
·         Details about routes and times at http://www.scapsite.org/ride.php

Please drive safely and exercise caution in the construction zones.
                                                                                   

###

Friday, September 16, 2011

ROAD AND LANE CLOSURES SCHEDULED FOR SEP 18 - SEP 25

Here are the major scheduled road and lane closures for the areas between Salinas and North Monterey County from Sunday, September 18 through Sunday, September 25 - newest information is in red.


Night work on Highway 1 to Highway 68: September 18 - 22
·         Caltrans will close the Hwy 1 off ramp to Hwy 68 eastbound AND the westbound Hwy 68 connector to southbound Hwy 1 overnight from Sunday, September 18, through Thursday, September 22.
o   This closure will only be at night, between the hours of 8 p.m. and 5 a.m.
o    There will be a detour to southbound Hwy 1 via the Casa Verde off ramp.



Hwy 101/Airport Blvd Project: September 18 – September 25

·         CalWater will have a lane closure on Airport Blvd. at Moffett St.  on Monday, Sept 19,  and possibly Tuesday, Sept 20, from 9 am to 3 pm.
·         The closure is needed to install a water line. 


Prunedale Improvement Project: September 18 – September 25
·         PG&E will close one lane on Echo Valley Road from Hwy 101 to Tustin Rd on Monday, September 19, 2011 from 7:00 am to 4:00 pm to finished pole relocation.
o    Traffic heading toward Hwy 101 will be detoured to Tustin Rd,
o    Traffic from Hwy 101 will be allowed through.

  • Night work from Monday, Sept. 19 – Thursday, Sept. 22 on HWY 101 at Russell and Espinosa between the hours of 7:30 p.m. and 6 a.m. will close:
    • The left turn to Espinosa Rd from the northbound Hwy 101
    • The right turn to Russell Rd from northbound Hwy 101
    • The right turn to Espinosa Rd from southbound Hwy 101
    • Emergency responders will have access at all times.

  • Night work on HWY 101 at San Miguel Canyon on Monday, Sept. 19 – Thursday, Sept. 22 will close the following between the hours of 7:30 p.m. and 6 a.m.:
    • One northbound lane between Tustin and San Miguel Canyon
    • The northbound on ramp at San Miguel Canyon
    • The northbound off ramp at San Miguel Canyon
    • One southbound lane between San Miguel Canyon and Tustin
    • The southbound off ramp at San Miguel Canyon

·         Blackie Road remains closed from Highway 101 to Borromeo Drive for approximately two months.
o    During construction there will be no entrance to Blackie Road from either Highway 101 or Prunedale South Road.  (Please see graphic at the end of this news release.)
o    Blackie Road at Prunedale South Road will be closed to all but emergency response vehicles. 
o    The closure is necessary to install a new box culvert that will go underneath Blackie Rd.
o    More information about this closure is available at http://www.tamcmonterey.org


·         The Northbound HWY 101 on and off ramps at Russell/Espinosa will be closed between the hours of 8:30 a.m. and 3:30 p.m. until late September/early October, 2011.
o    Crews will be:
 - Widening and reconstructing North Main St. from Russell Rd to 1000 feet south of the Russell Rd/Main St. intersection;
 - Working on storm drainage systems and a traffic signal; and
 - Making improvements along Russell Rd. and Harrison Rd.
o    Work hours for this project will be from 8:30 a.m. – 3:30 p.m., Monday through Friday.
o    Flaggers will be in the area to direct traffic.


·         Cross Rd. in Prunedale is closed to through traffic for approximately six months; the road is open to residents and emergency responders.
o    Caltrans is removing the pavement, installing several new box culverts, and making improvements along Cross Rd. and Reese Circle.
o    Throughout this construction Cross Rd will be open for residents, but will be closed to through traffic.
o    Detour signs will be posted throughout the area.
o    During this period Granite Construction crews will be working from 7 a.m. to 3:30 p.m., Mondays through Fridays.

Highway 68: September 18 – September 25
·         Monterey County Public Works continues its work along HWY 68 and San Benancio, which will go on until December 2011. This work is being done during the day; drivers should be alert. Most work will be done behind the concrete barriers that are set up, but minor delays can be expected.

UPCOMING PROJECTS
Highway 68 through Downtown Salinas: Delayed until September 26
·         The five-mile project to overlay Hwy. 68 from River Road to Work Street in Salinas has been delayed; the work is now scheduled to begin Monday, September 26.
o    Work will consist of daytime lane and ramp closures from 8:30 am to 4 pm, Mondays through Thursdays; and from 8:30 am to 1 pm on Fridays.
o    Overnight work may also take place between 6 pm and 7 am during the week.
o    Up to 10-minute delays are anticipated with the daytime closures. 
o    This project goes through downtown Salinas.
o    There will be reduced or no parking in this construction zone due to micro-surfacing of the pavement.

Please drive safely and exercise caution in the construction zones.

Thursday, September 8, 2011

ROAD AND LANE CLOSURES SCHEDULED FOR SEP 11 - SEP 18

Here are the major scheduled road and lane closures for the areas between Salinas and North Monterey County from Sunday, September 11 through Sunday, September 18 - newest information is in red.

Highway 68 connector to southbound Highway 1: September 12
·         Caltrans will close the westbound  Hwy. 68 connector to southbound Hwy. 1 from 9 a.m. to 3 p.m. on Monday, September 12.

     Caltrans will close the Hwy 1 off ramp to Hwy 68 eastbound from 9 a.m. to 3 p.m.
o   There will be a detour to southbound Hwy 1 via the Casa Verde off ramp.

Highway 1 to Highway 68: September 13 - 15
·         Caltrans will close the Hwy 1 off ramp to Hwy 68 eastbound AND the westbound Hwy 68 connector to southbound Hwy 1 overnight from Tuesday, September 13, through Thursday, September 15.
o   This closure will only be at night, between the hours of 8 p.m. and 5 a.m.
o    There will be a detour to southbound Hwy 1 via the Casa Verde off ramp.


Highway 68 through Downtown Salinas: September 12 – 18
·         A five-mile project to overlay Hwy. 68 from River Road to Work Street in Salinas will begin Monday, September 12.
o    Work will consist of daytime lane and ramp closures from 8:30 am to 4 pm, Mondays through Thursdays; and from 8:30 am to 1 pm on Fridays.
o    Overnight work may also take place between 6 pm and 7 am during the week.
o    Up to 10-minute delays are anticipated with the daytime closures. 
o    This project goes through downtown Salinas.
o    There will be reduced or no parking in this construction zone due to micro-surfacing of the pavement.



Prunedale Improvement Project: September 11 – September 18
·         Blackie Road remains closed from Highway 101 to Borromeo Drive for approximately two months.
o    During construction there will be no entrance to Blackie Road from either Highway 101 or Prunedale South Road.  (Please see graphic at the end of this news release.)
o    Blackie Road at Prunedale South Road will be closed to all but emergency response vehicles. 
o    The closure is necessary to install a new box culvert that will go underneath Blackie Rd.
o    More information about this closure is available at http://www.tamcmonterey.org


  • Night work on HWY 101 at Russell and Espinosa between the hours of 7:30 p.m. and 6 a.m. will close:
    • The left turn to Espinosa Rd from the northbound Hwy 101
    • The right turn to Russell Rd from northbound Hwy 101
    • The right turn to Espinosa Rd from southbound Hwy 101


  • Night work on HWY 101 at San Miguel Canyon between the hours of 7:30 p.m. and 6 a.m. will close:
    • One northbound lane between Tustin and San Miguel Canyon
    • The northbound on ramp at San Miguel Canyon
    • The northbound off ramp at San Miguel Canyon
    • One southbound lane between San Miguel Canyon and Tustin
    • The southbound off ramp at San Miguel Canyon


·         The Northbound HWY 101 on and off ramps at Russell/Espinosa will be closed between the hours of 8:30 a.m. and 3:30 p.m. until late September/early October, 2011.
o    Crews will be:
§  Widening and reconstructing North Main St. from Russell Rd to 1000 feet south of the Russell Rd/Main St. intersection;
§  Working on storm drainage systems and a traffic signal; and
§  Making improvements along Russell Rd. and Harrison Rd.
o    Work hours for this project will be from 8:30 a.m. – 3:30 p.m., Monday through Friday.
o    Flaggers will be in the area to direct traffic.


·         Cross Rd. in Prunedale is closed to through traffic for approximately six months; the road is open to residents and emergency responders.
o    Caltrans is removing the pavement, installing several new box culverts, and making improvements along Cross Rd. and Reese Circle.
o    Throughout this construction Cross Rd will be open for residents, but will be closed to through traffic.
o    Detour signs will be posted throughout the area.
o    During this period Granite Construction crews will be working from 7 a.m. to 3:30 p.m., Mondays through Fridays.


Highway 68: September 11 – September 18
·         Monterey County Public Works continues its work along HWY 68 and San Benancio, which will go on until December 2011. This work is being done during the day; drivers should be alert. Most work will be done behind the concrete barriers that are set up, but minor delays can be expected.