ROAD AND LANE CLOSURES SCHEDULED FOR AUG 28 - SEP 5


Here are the major scheduled road and lane closures for the areas between Salinas and North Monterey County from Sunday, August 28, through Monday, September 5 - newest information is in red.


Highway 101/Airport Boulevard Project: August 29 – August 31
·         Night work on HWY 101 will close one southbound lane between Sanborn Rd and Abbott St from August 29 – August 31; the lane closure will be from 9 p.m. to 6 a.m.
·         This closure is to remove the k-rail from the southbound onramp so it can be reopened.


Highway 1/Salinas Road Project: August 28 – September 5
·         Northbound and southbound traffic on HWY 1 will have access to Salinas Road again beginning on Thursday, September 1.
o    Drivers on Salinas Rd will be able to go either north or south on to the HWY 1 detour.
o    North and south bound drivers on the HWY 1 detour will be able to turn on to Salinas Rd.


Prunedale Improvement Project: August 29 – September 2
  • Night work on HWY 101 at San Miguel Canyon each night between the hours of 7:30 p.m. and 6 a.m. will close:
    • One northbound lane between Tustin and San Miguel Canyon
    • The northbound on ramp at San Miguel Canyon
    • The northbound off ramp at San Miguel Canyon
    • One southbound lane between San Miguel Canyon and Tustin
    • The southbound off ramp at San Miguel Canyon


·         Night work along  HWY 101 near Russell and Espinosa will also result in lane closures between the hours of 7:30 p.m. and 6 a.m.:
o    One Northbound lane between Russell/Espinosa and Ralph Lane.
o    One Southbound lane between Ralph Lane and Russell/Espinosa.
o    The Northbound off-ramp at Russell/Espinosa
o    The Southbound off-ramp at Russell/Espinosa


  • PG&E will have the westbound lane of Crazy Horse Canyon Rd. between HWY 101 and Executive Drive closed on Friday, September 2, from 7 am to 3 p.m. 
    • There will be flaggers for one-way traffic control.
    • This closure is to string overhead wire across the road. 


·         The Northbound HWY 101 on and off ramps at Russell/Espinosa will be closed between the hours of 8:30 a.m. and 3:30 p.m. until late September/early October, 2011.
o    Crews will be:
§  Widening and reconstructing North Main St. from Russell Rd to 1000 feet south of the Russell Rd/Main St. intersection;
§  Working on storm drainage systems and a traffic signal; and
§  Making improvements along Russell Rd. and Harrison Rd.
o    Work hours for this project will be from 8:30 a.m. – 3:30 p.m., Monday through Friday.
o    Flaggers will be in the area to direct traffic.


·         Cross Rd. in Prunedale is closed to through traffic for approximately six months; the road is open to residents and emergency responders.
o    Caltrans is removing the pavement, installing several new box culverts, and making improvements along Cross Rd. and Reese Circle.
o    Throughout this construction Cross Rd will be open for residents, but will be closed to through traffic.
o    Detour signs will be posted throughout the area.
o    During this period Granite Construction crews will be working from 7 a.m. to 3:30 p.m., Mondays through Fridays.


Highway 68: August 28 – September 5
·         Monterey County Public Works continues its work along HWY 68 and San Benancio, which will go on until December 2011. This work is being done during the day; drivers should be alert. Most work will be done behind the concrete barriers that are set up, but minor delays are possible.



****Other Events That May Affect Traffic****
  • August 28: Aromas Day (http://aromasday.info/default.aspx) in downtown Aromas will have portions of Carpenteria Rd, Rose Ave, Bardue St, Blohm Ave, and Marcus St closed from 9 a.m. to 4 p.m.. 


Please drive safely and exercise caution in the construction zones.
                                                                                   