Friday, July 19, 2013

Road and lane closures for June 21 - July 28

MONTEREY COUNTY – Here are the major scheduled road and lane closures for Monterey County from Sunday, July 21, through Sunday, July 28, 2013 – newest information is in red. Please keep in mind that construction work is weather-dependent.

Highway 1/Rocky Creek Viaduct Project:  July 22 – July 26
  • Daytime roadwork on Highway 1 continues next week from 7 a.m. to 5 p.m. Monday, July 22 through Friday, July 26.
  • There will be A FULL OVERNIGHT CLOSURE of Hwy. 1 on Wednesday, July 24 and Thursday, July 25 from 9 p.m. to 7 a.m.
  • No overnight closures will occur on Friday/Saturday nights. 
Highway 1 at Rocky Creek has one-way signalized traffic control 24/7. Traffic will be stopped for 10 minutes at a time during daytime and nighttime roadwork.

Highway 1 through Big Sur: July 22 – July 26
  • Day time drainage clearing and shoulder work the Big Sur coast between Buck Creek Bridge and Garrapata Creek Bridge from 8 a.m. to 3 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Highway 101 Gonzales and Soledad:  July 22 – July 26
  • Daytime survey work on Highway 101 from La Gloria Road south will result in alternating lane closures—northbound and southbound—between 7 a.m. and 3:30 p.m.
  • Motorists can expect delays of approximately 10 minutes.
Prunedale Improvement Project – Ralph Lane to Pesante Road:  July 22 - 26
  • Nighttime work on Highway 101 from Ralph Lane to Pesante Road will close one lane each direction between 8 p.m. and 6 a.m.
  • The closure is needed for crews to conduct work on the median barrier.
  • Motorists can expect delays of approximately 10 minutes.
San Juan Road Interchange: Day and Night Work July 22 – July 26
·        Daytime work on Highway 101 from Dunbarton Road to Rocks Road will close one lane each direction between the hours of 10 a.m. and 2 p.m. on Wednesday, July 24, and Thursday, July 25.
·       Motorists can expect delays of approximately 10 minutes.
·       Night work continues this week with trucks hauling dirt across Highway 101 between San Juan Road to Cole Road.
·       Motorists can expect delays of approximately 5 minutes.

Highway 146 – Pinnacles: July 23 - 26  
  • Daytime pavement work on Highway 146 from Ramus Road to the San Benito County line between the hours of 9 a.m. to 1 p.m. on Tuesday July 23, through Friday, July 26.
  • Motorists can expect delays of approximately 10 minutes.
Highway 183 – Salinas: July 22 - 23  
  • Daytime shoulder work on Highway 183 from Stone Street to Lincoln Avenue in downtown Salinas between the hours of 8:30 a.m. to 3 p.m. on Monday July 22, and Tuesday, July 23.
  • Motorists can expect delays of approximately 5 minutes.
Highway 198 – San Lucas:  July 22 - 26 
  • Daytime pavement work on Highway 198 East of San Lucas from Peach Tree Valley Road to Griffin Road between the hours of 8 a.m. to 3 p.m.
  • Motorists can expect delays of approximately 10 minutes.
***UPCOMING CLOSURE:  Left Turn Lanes on Highway 101 at Messick Road & Tustin Road ***
·        Crews will install K-Rail along the center median of Highway 101 at Messick Road and at Tustin Road on August 4, closing the left turn lanes.
·       The closure will increase safety by eliminating left turns across the busy Highway 101 in this area. The closures will also allow construction work to begin on the permanent center median barrier.
·       Travelers should detour to San Miguel Canyon Road.