Here are the major scheduled
road and lane closures for the areas between Salinas and North Monterey
County from Sunday, June 3, through
Sunday, June 10, 2012– newest information is in red. Please keep in mind that construction work is
weather-dependent.
Prunedale Improvement Project: June 4 – June
7
· Night work on Hwy 101, between Mallory Canyon and
Crazy Horse Canyon., will close one lane in each direction from Monday, June 4,
through Thursday, June 7. The lane closures will be between the hours of 7:30
p.m. and 6:30 a.m.
o
Crews will be working along the
shoulders.
Prunedale Improvement Project: Temporary
Closure of Harrison Rd. Continues
· On May 7 Caltrans closed Harrison Rd. – from Russell Rd. to Martines
Rd.; and the intersection at North Main St. and Russell Rd. for approximately
four months to all but local traffic and emergency response vehicles.
This closure is
necessary to install new drainage systems, new signals, and rebuild the entire
roadway. All businesses and places of
worship along Harrison Rd. and North Main St. are open during this
construction.
Construction
will go through September 9; during this time:
·
Harrison Rd., a portion of North Main St., and a
portion of Russell Rd. will be dirt and gravel;
·
Emergency response vehicles will have access at all
times;
·
Local traffic, including those going to businesses
in the area, will have access;
·
The speed limit in the construction
area will be reduced to 25 M.P.H.;
·
There will be traffic delays of up to 20 minutes –
especially along Harrison Rd.;
·
Water trucks will be used to keep
dust down;
·
There will be construction noise
during the day, with crews generally working from 7 a.m. to 4 p.m.
Prunedale
Improvement Project: Temporary Closure of Cross Rd.
· On May 10, Cross Rd. in Prunedale was closed to through
traffic for approximately three months; the road is open to residents and
emergency responders.
Caltrans is removing the pavement and making improvements along
Cross Rd. and Reese Circle.
o
Throughout this construction Cross Rd. will be
open for residents, but will be closed to through traffic.
o
Residents can use Pollock Lane to access
Pesante Rd. and Hwy 101
o
Detour signs will be
posted throughout the area.
o
During this period
Granite Construction crews will be
working from 7 a.m. to 3:30 p.m., Mondays through Fridays.