PIP Map

Friday, December 2, 2011

Update on Moro Rd. closure

The Moro Road closure scheduled for November has been moved to December 12

 Access to Oak Estates Dr., Marjorie Rd., and Oak Heights Dr. will be via Tustin Rd.


Granite Construction, Caltrans’ contractor for the 101/Prunedale Improvement Project (PIP), will permanently close the entrance and exit between Highway 101 and Moro Road during the week of December 12. The exact date of the closure is still to be determined, based on construction progress.

This closure was originally scheduled for November, but was moved to December due to construction delays.