ROAD AND LANE CLOSURES SCHEDULED FOR NOV 3 - NOV 13

Please note: I will be out of the office, in a class, on Friday, November 4, so if you have questions about the PIP I will not be able to reply until Monday.
Thank you,


Here are the major scheduled road and lane closures for the areas between Salinas and North Monterey County from Sunday, November 6, through Sunday, November 13 – newest information is in red.

101/Airport Blvd. Project: November 10
·         Night work on Hwy 101 will completely close the northbound lanes of Hwy 101 on Thursday, Nov. 10, from 9p.m. to 6 a.m.
o    Motorist will be detoured at Abbott St.  to Sanborn Rd. to Hwy 101;
o    Crews will be installing a bridge mounted sign. 


Highway 68 through Downtown Salinas: November 6 – November 13
·         Night work for the Highway 68 overlay project in Downtown Salinas will take place from Sunday, November 6, through Sunday, November 13, between the hours of 6 p.m. and 7 a.m.
o    Up to 10-minute delays are anticipated. 
o    This project goes through downtown Salinas.
o    There will be reduced or no parking in this construction zone due to micro-surfacing of the pavement.

Highway 1 to Highway 68: November 6 – November 13
·         There will be a night closure on the Highway 68 connector to southbound Highway 1, and the northbound Highway 1 off ramp to eastbound Highway 68, from Sunday, November 6, through Thursday, November 10, between the hours of 8 p.m. and 5 a.m.

·         There will also be daytime closures on the Highway 68 connector to southbound Highway 1, and the northbound Highway 1 off ramp to eastbound Highway 68, from Tuesday, November 8, through Thursday, November 10, between 9 a.m. and 3 p.m.
o   The detour is available via Casa Verde.

·         Furthermore, there will be a daytime lane closure on Highway 68 near Toro Park, on Monday, November 7, through Thursday, November 10, from 8:30 a.m. to 4:00 p.m., and on Friday, November 8, from 8:30 a.m. to 1 p.m.


Prunedale Improvement Project: November 6 – November 13
  • Night work will close lanes of HWY 101 between Tustin and San Miguel Canyon on November 7 – November 9, between the hours of 9 p.m. and 5 a.m.
    • Traffic will be crossed over to the opposite side of the highway.
    • Detour signs will clearly indicate the traffic crossover details. 
    • CHP will be in the area during the crossovers.

  • Night work will close lanes of HWY 101 between Ralph Lane and Prunedale South Road on November 9 – November 10, between the hours of 9 p.m. and 5 a.m.
    • Traffic will be crossed over to the opposite side of the highway.
    • Detour signs will clearly indicate the traffic crossover details. 
    • CHP will be in the area during the crossovers.


·         On Thursday, November 3, Granite Construction, Caltrans’ contractor for the 101/Prunedale Improvement Project (PIP), will permanently close the Oak Heights entrance off of U.S. Highway 101.
o    The new access to Oak Heights from Highway 101 will be from Moro Road.
§  From southbound Highway 101, drivers will turn right on to the Moro Road exit, turn right on Moro Road and follow it to the end where they can turn left onto Oak Heights.
§  From northbound Highway 101, drivers will turn left on to the Moro Road exit, turn right on Moro Road and follow it to the end where they can turn left onto Oak Heights.


·         On Monday, Nov. 7, Granite Construction, Caltrans’ contractor for the 101/Prunedale Improvement Project (PIP), will close the entrance and exit between Highway 101 and Russell Road.
o    Highway 101 traffic heading to Russell Road will need to exit the highway at Boronda Road and head east to Main Street, then turn left on Main Street to Russell Road.


Carmel Valley Road Overlay Project: November 6 – November 13
  • This is a Monterey County road construction project on Carmel Valley Road from Dorris Drive to Rancho Fiesta, which will go through the end of December.
    • Work is from 8 a.m. to 4:30 p.m.
    • There will be some lane closures;
    • Traffic controls will be in place,
    • Expect five minute delays. 


Highway 68: November 6 – November 13
·         Monterey County Public Works continues its work along HWY 68 and San Benancio, which will go on until December 2011. This work is being done during the day; drivers should be alert. Most work will be done behind the concrete barriers that are set up, but minor delays can be expected.


Please drive safely and exercise caution in the construction zones.
                                                                                  

###